Главная / SZS D-type Water-tube Oil & Gas Boilers — Installation, Commissioning & Maintenance Manual

SZS D-type Water-tube Oil & Gas Boilers — Installation, Commissioning & Maintenance Manual

This manual covers the SZS series D-type double-drum water-tube boilers, fired on natural gas, LPG, light oil or heavy oil, in saturated steam ratings of 10 to 40 t/h at 1.6 and 2.5 MPa and in hot-water ratings of 7, 14 and 29 MW. It is written for the plant engineer, shift operator and maintenance technician who install, commission, run and inspect the unit. Every maintenance task carries a measurable acceptance limit, and values fixed by the ordered burner or water-treatment plant are flagged for confirmation against the site-specific manual.

Document code YX-MAN-SZS
Revision 1.0
Issue date 2026-11
Applies to SZS10-1.6 to SZS40-2.5; SZS7 to SZS29 hot water
Language English

1. Scope and model coverage

The SZS is a shop-assembled D-type boiler. Membrane water walls enclose the furnace on three sides; the fourth side is the convection bank between the drums, and gas leaves through the rear flue past the economiser and air preheater. The burner mounts on the front wall and fires horizontally along the furnace. A superheater can be fitted in the rear pass; this manual covers the saturated and hot-water variants, and superheated units follow the supplementary data sheet.

Model Capacity Design pressure and temperature Fuel Typical duty
SZS10-1.6 10 t/h 1.6 MPa, 204 °C saturated Gas, LPG, light oil Two-shift process steam
SZS15-1.6 15 t/h 1.6 MPa, 204 °C saturated Gas, light or heavy oil Continuous process steam
SZS20-2.5 20 t/h 2.5 MPa, 226 °C saturated Gas, light oil Process steam, small turbine supply
SZS25-2.5 25 t/h 2.5 MPa, 226 °C saturated Gas, light or heavy oil Base-load industrial steam
SZS30-2.5 30 t/h 2.5 MPa, 226 °C saturated Gas, light oil District heat and process steam
SZS40-2.5 40 t/h 2.5 MPa, 226 °C saturated Gas, light oil Large plant base load
SZS7-1.0/95/70 7 MW 1.0 MPa, 95/70 °C Gas, light oil Low-temperature district heating
SZS14-1.6/130/70, SZS29-1.6/130/70 14 and 29 MW 1.6 MPa, 130/70 °C Gas, light or heavy oil Pressurised hot-water networks

Capacity follows the saturated-steam equivalence of about 0.7 MW per t/h: 10 t/h is about 7 MW and 40 t/h about 28 MW. Steam models are described on the SZS oil and gas steam boiler page, hot-water models on the hot-water boiler page. Excluded: civil works, chimney steelwork beyond the outlet flange, fuel storage, the water-treatment plant unless ordered with the boiler, and electrical work upstream of the panel terminals. Burner gas-train settings follow the burner manual.

2. Site and utility requirements before delivery

Confirm every item below before dispatch. A shortfall found after delivery moves cost and delay to the site, and rear clearance cannot be corrected once the house is built. Record the values on the readiness sheet and return a signed copy. If demand is not yet fixed, size against the load profile using the load-duration method on the capacity selection pages.

Item Requirement Tolerance and notes
Foundation and plinth Reinforced concrete to the general arrangement, bolts cast in Level ±3 mm, bolt centres ±2 mm, 25 mm grout
Burner front clearance Space to swing the burner open and remove the nozzle At least 1.5 m or burner length plus 0.5 m
Rear clearance Access for economiser and preheater withdrawal 2.0 m behind the flue, 0.8 m at drum ends
Headroom Above drum, safety valve discharge and lifting beam 1.0 m above the highest valve
Ventilation Combustion and cooling air through two louvres Free area ≥ 1.2 × burner air demand; room ≤ 45 °C
Feed water Hardness ≤ 0.03 mmol/L, oxygen ≤ 0.05 mg/L, pH 8.8–9.3, iron ≤ 0.1 mg/L Deaerator above 6 t/h; softener sized for make-up plus blowdown
Boiler water pH 10–12, conductivity per drum pressure ≤ 4000 µS/cm at 1.6 MPa, ≤ 3000 µS/cm at 2.5 MPa
Fuel gas 20–35 kPa at the train inlet +15% / −10%; calorific value within the burner data
Light oil 0.6–1.0 MPa at the burner, viscosity ≤ 5 mm²/s Ring main with return; heavy oil heated to 90–110 °C
Flue and chimney Balanced draft, furnace −20 to −50 Pa at full load Stack sized by dispersion calculation
Electrical supply 380 V, three-phase, 50 Hz, neutral earthed Voltage ±5%, earth resistance ≤ 4 Ω
Drainage and blowdown Vented pit of at least 2 m³ with a cooling path Discharge below 60 °C; blowdown line DN50 minimum

3. Installation sequence

The sequence assumes a cured plinth and a weather-tight house. Do not start piping until the boiler is grouted and the expansion indicators are set, ; later jacking destroys the zero reference.

  1. Survey the plinth and mark the centre lines and bolt positions. Acceptance: level ±3 mm, diagonals equal within 5 mm.
  2. Unload with a crane rated for the shipping weight, lifting only from the marked lugs. Acceptance: no casing or tube distortion.
  3. Set the boiler on packers and align the drum axis. Acceptance: centre line ±2 mm in both directions.
  4. Grout the base frame with non-shrink grout and cure before filling. Acceptance: no voids at the corners.
  5. Fit the expansion indicators and set zero at 20 °C. Acceptance: pointer on zero, scale readable from the operating floor.
  6. Assemble the rear flue, economiser and air preheater with new gaskets. Acceptance: 5 kPa air test with soap solution shows no bubbles.
  7. Erect duct and chimney, then measure draft with the induced-draft fan running. Acceptance: −20 to −50 Pa at the furnace outlet.
  8. Install the burner and check nozzle protrusion and throat clearance. Acceptance: protrusion ±2 mm, door swings 90° clear of the casing.
  9. Pipe the feed line from deaerator through pump and economiser to the drum, with a non-return valve. Acceptance: no load on the drum nozzles.
  10. Install the steam or hot-water header on spring hangers with a 1:100 fall. Acceptance: hangers carry the pipe weight, no cold pull at the flange.
  11. Mount safety valves, pressure gauges with syphons, thermowells and level transmitters. Acceptance: gauge range 1.5–2 times design pressure.
  12. Complete the electrical work to the panel terminals and earth the frame. Acceptance: insulation ≥ 1 MΩ at 500 V, earth ≤ 4 Ω.
  13. Fill with treated water at 20–50 °C, vent the drum, raise to working pressure. Acceptance: no weeping at manholes or expanded joints.
  14. Hydrostatic test at 1.5 times design, hold 30 minutes, drain and flush. Acceptance: no pressure drop and no permanent deformation.
Lifting and riggingThe shipping weight excludes water, refractory and burner. Use four-point lifting with the marked lugs and a spreader beam, and keep personnel out of the swing zone. Never lift by the membrane walls or sling from a drum nozzle; a deformed nozzle cannot be repaired to the pressure-part standard.
Expansion and anchor pointsThe front drum support is fixed and the rear support slides on stainless pads. Indicators are zeroed at 20 °C, and the chart gives the expected reading at each drum metal temperature, about 12 mm at full load on the 2.5 MPa units. Do not weld brackets or cladding to the casing or membrane wall, and keep the sliding pads free of grout and debris.

4. Commissioning and handover

Commissioning starts after the hydrostatic test and internal inspection. Fill with treated water at 20–50 °C, vent every high point, and confirm that the gauge glass and transmitter agree within 5 mm before lighting.

The hydrostatic test pressure is 1.5 times design: 2.4 MPa for the 1.6 MPa units and 3.75 MPa for the 2.5 MPa units. Hold for 30 minutes at a water temperature of 20–50 °C with a calibrated gauge on the drum and the safety valves gagged. Acceptance is no pressure drop, no weeping at any joint and no visible deformation, following the practice of GB/T 16508 and TSG G0001.

Set the burner at low fire, then high fire, on the fuel named in the order. For natural gas, target 3.0–3.5% oxygen at low fire and 3.0% at high fire, about 15–20% excess air and 9.5–10.5% carbon dioxide; carbon monoxide must stay below 50 ppm. Bring stack temperature within 20 °C of design at rated load and record every damper position on the commissioning curve; later maintenance is judged against it. The matched burner package manual governs gas-train pressures and scanner settings.

Interlock Simulated condition Expected result
Extra-low water level Drain the float chamber until the LL electrode is dry Burner trips within 3 s, alarm sounds, reset blocked until level returns
High water level Raise level above the HH electrode Feed pump stops, alarm sounds, burner stays on
Flame failure Close the manual gas cock at low fire Main valve closes within 3 s, post-purge runs, lockout without auto-restart
Low gas pressure Drop train pressure below 50% of set point Burner trips, alarm latched, purge before restart
High gas pressure Raise pressure above 110% of set point Burner trips, alarm latched, relief not lifted
High steam pressure Lower the pressure switch set point below working pressure Trip at set pressure plus 0.05 MPa; safety valve must not lift
Combustion air failure Stop the forced-draft fan at low fire Trip within 2 s, damper closes, alarm sounds
Low feed-water pressure Throttle the feed valve below 80% of set point Burner trips, standby pump starts where fitted

Run 4 hours at 50–75% load, then 24 hours at normal plant load, logging level, steam pressure and temperature, feed-water and stack temperature, oxygen, carbon monoxide and draft hourly. Acceptance: no unexplained trip, stack temperature stable within 10 °C, level held within ±10 mm on automatic control, no leaks. Handover documents are the as-built arrangement, pressure-part material certificates, hydrostatic record, safety valve setting record, interlock test sheet, burner commissioning curve, wiring diagram and this manual.

5. Normal operation

Start-up from cold. Confirm normal level, open vent and burner off. Purge for 5 minutes at 25% air flow, five volume changes. Light at minimum fire, hold until 0.2 MPa, then close the vent. Raise pressure at no more than 0.03 MPa per minute and keep the drum top-to-bottom difference below 40 K; working pressure takes 2–3 hours. Load at no more than 10% of capacity per minute.

Start-up from hot standby. With the drum at 0.3–0.5 MPa and level at −50 mm, purge for 5 minutes, light and raise load at 10% per minute, keeping drum metal rise below 1.0 °C per minute. After 8 hours on standby, check the gauge glass before purging; a leaking non-return valve can fill the drum.

Parameter Normal band Action if outside
Drum water level ±10 mm of the normal line Compare with gauge glass, blow down, check transmitter
Steam pressure 1.6 ± 0.05 MPa or 2.5 ± 0.08 MPa Check modulation and pressure transmitter
Steam temperature Saturation ±5 °C (204 or 226 °C) Check for carryover
Feed water after economiser At least 40 K below saturation Check economiser fouling and deaerator
Stack temperature Within 20 °C of the clean baseline Blow soot, check for scale
Oxygen at outlet 3.0–3.5% Trim air damper, check analyser
Carbon monoxide ≤ 50 ppm Check nozzle, flame shape and excess air
Furnace draft −20 to −50 Pa Check ID fan, damper and flue blockage
Drum metal difference ≤ 40 K top to bottom Reduce firing rate, extend warm-up

Normal shutdown. Reduce to 20% load at 10% per minute, purge 5 minutes, close the main valve and stop the burner. Run the fan 10 minutes to clear the furnace and flue, then close the air damper. Top up to normal level because the water shrinks as it cools, and blow down only below 0.2 MPa.

Emergency shutdown. Press the emergency stop, which closes the main fuel valve and trips the burner. Keep the fan running if unburnt fuel is suspected, and do not open the furnace until a 5-minute purge is complete. Never dump water from a hot boiler or lift a safety valve by hand to speed up pressure reduction. Record the cause, pressure and level.

Lay-up over 30 days. Wet lay-up: fill completely with condensate or demineralised water dosed to pH 10.5–11.5 with 200 mg/L oxygen scavenger, blanket with nitrogen at 0.05–0.1 MPa, and check chemistry weekly. Dry lay-up: drain and dry, place 1.0 kg of desiccant per cubic metre of water volume in trays on the drum, seal the manholes and keep relative humidity below 40%, renewing the desiccant monthly.

6. Maintenance schedule

Intervals assume gas or light oil, treated water and 6,000 base-load hours a year; halve them for heavy oil or more than two starts a day. The energy consumption pages give the baseline stack temperature and efficiency; the US Department of Energy steam resources give a wider audit benchmark.

6.1 Daily (each shift)

Task What to check / acceptance Tool or reference Who
Drum level Gauge glass within ±10 mm of the transmitter; blow the glass until clear Gauge glass, trend Operator
Pressure and temperature Within the section 5 band; within 5 °C of saturation Panel, calibrated gauge Operator
Burner and gas train Flame stable; scanner signal ≥ 60% of commissioning value; gas 20–35 kPa Scanner display, gauge Operator
Oxygen and stack temperature O2 3.0–3.5%; stack within 20 °C of baseline Analyser, thermocouple Operator
Soot blowers Rear bank and economiser blowers once per shift on oil, once per 8 h on gas above 80% load; steam 0.8–1.0 MPa Blower control Operator
Bottom blowdown 10–15 s; conductivity ≤ 4000 µS/cm (1.6 MPa) or 3000 µS/cm (2.5 MPa) Valve, conductivity meter Operator
Feed pump and deaerator Current within 10% of commissioning; deaerator 104 ± 2 °C; oxygen ≤ 0.05 mg/L Ammeter, DO meter Operator
Expansion indicators Reading within ±2 mm of the chart value for the drum temperature Indicator, chart Operator
Leaks and casing No steam, water or gas leak; casing ≤ ambient plus 25 K Visual, IR thermometer Operator

6.2 Monthly

Task What to check / acceptance Tool or reference Who
Level transmitter calibration Five points at 0/25/50/75/100%; error ≤ ±5 mm; contacts at ±50 and ±75 mm Calibrator, sight glass Instrument technician
Safety valve manual lift Lift at 75% of set pressure or above; reseats without wire drawing Lever, pressure gauge Shift engineer
Flame scanner and igniter Lens clean, signal ≥ 60%, spark gap 2.5 ± 0.2 mm Scanner test, feeler gauge Technician
Air preheater cold end Metal ≥ 130 °C on oil and ≥ 90 °C on gas; drain flowing; no acid smear Thermocouple, sight glass Technician
Feed-water analysis Hardness ≤ 0.03 mmol/L, iron ≤ 0.1 mg/L, pH 8.8–9.3; softener cycle verified Lab kit, softener log Chemist
Burner linkage Damper positions match the curve at low, mid and high fire; backlash ≤ 2° Curve sheet, protractor Technician
Alarm annunciation Every alarm tested; horn and beacon operate Test list Instrument technician
Soot blower travel Full stroke without sticking; nozzles aligned within ±3 mm Manual stroke, drawing Fitter

6.3 Quarterly and semi-annual

Task What to check / acceptance Tool or reference Who
Water-side inspection (semi-annual) Open handholes; scale ≤ 0.5 mm, no sludge blanket in the lower drum Boroscope, scraper Boiler engineer
Steam purity Steam conductivity ≤ 1 µS/cm above feed water Sample cooler, meter Chemist
Flue-gas analysis CO ≤ 50 ppm, excess air 15–20%, NOx within permit Flue analyser Technician
Casing and refractory survey No hot spot above ambient plus 25 K; front-wall cracks ≤ 3 mm IR camera, crack gauge Boiler engineer
Electrical inspection Insulation ≥ 1 MΩ at 500 V, earth ≤ 4 Ω, currents balanced within 5% Insulation and earth testers Electrician
Drum supports (semi-annual) Sliding pads free, anchor nuts tight, 3 mm clearance at guides Torque wrench, feeler Fitter
Air preheater tightness Gas-to-air leakage ≤ 5% by oxygen rise across the unit O2 readings Technician

6.4 Annual shutdown inspection

Task What to check / acceptance Tool or reference Who
Drum internals and steam-water separator Open both manholes, clean internals, inspect separator vanes, baffles, feed pipe and blowdown pipe for cracks or distortion; gaps ±1 mm of drawing; renew manhole gaskets Boroscope, drawing, gaskets Service engineer
Tube wall thickness survey Ultrasonic survey of water walls, convection bank and economiser; full survey every 3 years, 10% spot check between, concentrated on the burner zone; alarm at 90% of nominal (4.5 mm), replace below 80% (4.0 mm) UT gauge, tube chart NDT inspector
Hydrostatic test where due 1.5 × design (2.4 or 3.75 MPa) for 30 minutes; no drop, no weeping Test pump, master gauge Engineer and inspector
Safety valve overhaul Strip and lap seats, bench-set to ≤ design pressure on a certified gauge, accumulation ≤ 10%, re-seal and record Bench rig, master gauge Service engineer
Soot blower overhaul Lance straight within 2 mm, nozzles clear, chain tension correct, limit switches working Straight edge, chain gauge Fitter
Air preheater cold end Clean elements; wall loss ≤ 30%, replace beyond; check expansion plates Thickness gauge Fitter
Refractory and front wall Cracks ≤ 3 mm, no spalling at the throat; patch with matching castable Hammer test, castable Refractory mason
Expansion indicators and drum supports Record cold reading, compare with the last hot reading, reset zero if within ±1 mm of chart; rollers free Indicator, chart Boiler engineer
Deaerator and feed system Internals clean, nozzles clear, oxygen ≤ 0.05 mg/L after restart, safety valve free Inspection cover, DO meter Boiler engineer
RecordsKeep the shift log, water-analysis sheet, interlock test sheet and inspection reports for at least 3 years, and the tube survey for the life of the boiler. Escalate any reading beyond an acceptance limit on the same shift; a repeated minor deviation is a trend, and a trend precedes a tube failure.

7. Troubleshooting

Symptom Likely cause Check Remedy
Pressure falls at constant load Fouled tubes, wrong air/fuel ratio Stack temperature, O2, burner position Blow soot, trim ratio, check modulation signal
Stack temperature 30 °C above baseline Soot on the bank, water-side scale O2 before and after the bank, water side Operate blowers, descale, reseat baffles
Wet steam or carryover High solids, damaged separator, high level Steam conductivity, internals, level trend More blowdown, repair separator, lower level
Low-water trip on start-up Transmitter drift, closed feed valve, air lock Glass against transmitter, pump pressure Recalibrate, open valve, vent feed line
Burner lockout during a run Dirty scanner, gas pressure excursion Scanner signal, train pressure, flame shape Clean scanner, reset after full purge
Make-up rises and pressure drops Tube or expanded-joint leak Water balance, hydro test, UT survey Isolate, locate by section, replace or re-expand
Acid smell at the preheater Cold end below dew point at low load Cold-end temperature, drain flow Raise inlet air temperature, keep load above 30%
High carbon monoxide Lean flame, dirty nozzle, closed secondary air O2 and CO together, nozzle condition Clean nozzle, open secondary air, re-trim
Safety valve weeps Seat damage, debris, set pressure low Setting record, seat condition Lap or replace seat, bench-set and re-seal

8. Spare parts and service

Hold the following for the first year; add a second set if there is no standby unit.

Item Quantity Notes
Manhole and handhole gaskets Two full sets Graphite or spiral-wound; never reuse a compressed gasket
Gauge glass and packing Two sets Match glass length to the fitting
Level electrodes One set Same model, calibration sheet kept
Burner nozzle and electrodes One set Size per burner data sheet
Flame scanner One Interchangeable with the fitted unit
Gas train filter element Two Renew at each annual shutdown
Soot blower nozzles Four Match the lance thread
Refractory castable 50 kg Same grade as the front wall, stored dry

Stock descaler, oxygen scavenger, softener salt and anti-seize compound. Order by model, serial number, drawing number and position number; a nameplate photograph shortens the check. The feed-water pump and control cabinet are listed separately when supplied as part of the package. Henan Yongxing Special Equipment Co., Ltd. acknowledges parts enquiries within one working day, dispatches stock items within two, and puts an engineer on site within five working days for a pressure-part or control fault; emergency cover is on the number in the order confirmation.

9. Document control

Revision Date Change
A 2019-06 First issue, SZS10 to SZS40
B 2022-03 Added hot-water models, O2 trim and the 3-year ultrasonic survey
C 2025-11 Revised maintenance tables, valve re-sealing and lay-up limits

This file is hash-verified. The SHA-256 digest of the published document is shown on the verification page; a copy whose digest does not match is uncontrolled. Check the digest at the manual verification page before relying on a printed copy, and compare the revision letter with the table above; earlier revisions remain in the manual library. The boiler is designed and built to GB/T 16508 and TSG G0001, with third-party inspection available on request; no other certification is implied.

Burner settings, water limits and chimney draught are fixed per order, so ask for the site-specific manual with your serial number before the first annual inspection. Send the serial number, model and a nameplate photograph through the contact page for the matching document and current spare-parts list.

Request the site-specific manual

Document control and download

Document

YX-MAN-SZS · revision 1.0 · issued 2026-11
Applies to the model families listed in section 1.

Download

Manual PDF · 253 KB
Print-ready A4, same content as this page.
Weekly maintenance log sheet · one page for the shift file.

SHA-256 940f007ea722c9c6698924cd3e16b06ac6f978f3ced3a2097ce71c71d0bbdc96

This fingerprint is calculated from the PDF file itself. Verify it on the verification page — the check runs in your browser, so an altered file cannot pass. A signed copy of the full manifest is published alongside it.

Key facts

  • YXBOILER is the global brand and manufacturing site of Henan Yongxing Boiler Manufacturing Co., Ltd., an industrial boiler and pressure-vessel manufacturer founded in 1981 in Henan, China.
  • Main products: steam boilers, hot-water boilers, thermal-oil heaters, biomass and coal-fired boilers, electric boilers, pressure vessels and autoclaves.
  • Serving customers in worldwide with selection, drawings, export packaging, installation guidance and spare parts.
  • Contact: WhatsApp +86 133 5377 2661 · [email protected].

Related on this site

Specifications, categories and further reading.

YXBOILER network

The same manufacturer, documented site by site.

Standards & references

Independent sources used in our engineering work.

YXBOILER — Global brand and manufacturing site. Last updated November 2026.