Accueil / DHX / SHX / QXX Circulating Fluidised Bed Boilers — Installation, Commissioning & Maintenance Manual

DHX / SHX / QXX Circulating Fluidised Bed Boilers — Installation, Commissioning & Maintenance Manual

This manual covers the circulating fluidised bed (CFB) family DHX, SHX and QXX: steam units from 10 t/h to 75 t/h and hot water units of 29 MW and 58 MW. It sets out the site services required before delivery, the erection and commissioning sequence, operating procedure from cold and from hot standby, the maintenance schedule with numeric acceptance limits, and fault-finding. It is written for boiler operators, plant engineers and maintenance planners responsible for a CFB unit burning coal gangue, washed coal, anthracite, biomass pellets or sludge blends.

Document code YX-MAN-CFBRevision 1.0Issue date 2026-11Applies to DHX10-1.6 to SHX75-3.82; QXX29 to QXX58Language English

1. Scope and model coverage

All three series share one principle: a dense bed fluidised by primary air, a fast riser, a hot cyclone returning solids through a loop seal, and a convection pass with superheater, economiser and air preheater. Fuel is crushed to 0–8 mm with no more than 30% below 2 mm, and limestone is fed for in-furnace desulphurisation at Ca/S 1.8–2.2. Steam and hot water duties share the furnace platform, so spares and practice carry across the range.

Model Capacity Design pressure / outlet Fuel Typical duty
DHX10-1.6 10 t/h (≈7 MW) 1.6 MPa, saturated 204 °C Coal gangue, washed coal Factory process steam, two shifts
DHX20-2.5 20 t/h (≈14 MW) 2.5 MPa, saturated 226 °C Coal gangue, anthracite Plant steam, daily cycling
SHX35-2.5 35 t/h (≈24.5 MW) 2.5 MPa, 226 °C or 400 °C superheat Washed coal, biomass pellets Process steam and small CHP
SHX45-2.5 45 t/h (≈31.5 MW) 2.5 MPa, 226 °C or 400 °C superheat Coal gangue with sludge co-firing Chemical and paper steam
SHX75-3.82 75 t/h (≈52.5 MW) 3.82 MPa rated (4.2 design), 450 °C Washed coal, anthracite Power and CHP, base load
QXX29-1.6/130/70 29 MW (≈41 t/h steam equivalent) 1.6 MPa, 130/70 °C water Coal gangue, biomass pellets District heating network
QXX58-1.6/130/70 58 MW (≈83 t/h steam equivalent) 1.6 MPa, 130/70 °C water Coal gangue, washed coal City heating, campus ring main

Excluded: site electrical works beyond the motor terminal boxes, civil and structural steel, the chimney and flue gas plant downstream of the boiler outlet, fuel yard handling before the day silo, and water treatment. The full boiler range and the coal-fired CFB steam boiler page give the commercial data behind this manual.

2. Site and utility requirements before delivery

Confirm every item before the foundation is poured. A CFB is taller and heavier than a packaged boiler of the same output and its ducts are large, so changes after erection are expensive. Return the signed utility schedule with the foundation approval.

Item Requirement Tolerance / notes
Foundation and plinth Reinforced concrete to the general arrangement loading plan Level ±5 mm overall, ±2 mm/m locally; bolts set from a template
Tube removal and access clearance 1.5 m at the front wall, 1.0 m at the side walls Clear to full height; no pipes inside the zone
Bed gun swing 1.2 m clear in front of the burner For gun withdrawal and nozzle cleaning
Boiler house ventilation 6 air changes per hour minimum Burner platform ≤40 °C in summer
Feed water Hardness ≤0.03 mmol/L, iron ≤0.1 mg/L, pH 8.5–9.5 Dissolved oxygen ≤0.05 mg/L after deaeration
Deaerator Required above 6 t/h evaporation 104 °C, 0.02 MPa gauge, 20 min storage at rating
Fuel 0–8 mm crushed, below 2 mm no more than 30% LHV 12–18 MJ/kg; moisture ≤12% at the feeder
Limestone 0–1 mm, CaCO3 ≥90% Dry, free-flowing, silo with 8 h buffer at full load
Flue and chimney Balanced draught, induced draught fan sized at 1.2× calculated flow Chimney height set by the dispersion study
Electrical supply 380 V, 50 Hz, three phase, neutral and earth Voltage ±5%, frequency ±1 Hz, earth resistance ≤4 Ω
Drainage and blowdown pit 2 m3 pit with quench connection Discharge below 80 °C before entering the drain

Water chemistry drives tube life. Hold boiler water pH 10–12, total alkalinity within 8 mmol/L, and conductivity to 3 000 µS/cm at 2.5 MPa or 2 000 µS/cm at 3.82 MPa. Blow down from the lower drum header, recording conductivity before and after, so the cycle is set by measurement rather than habit.

Fuel varies widely across gangue, washed coal and biomass, and the bed tolerates that only while the size band holds. Fines below 2 mm burn in the riser and load the cyclone; oversize above 8 mm drains unburnt, so check the crusher screen monthly. For biomass and waste fuels, IEA ash and moisture data cross-checks supplier certificates, and the capacity and steam data pages give derating curves for high-moisture fuel.

3. Installation sequence

The sequence below assumes the foundation has cured and the boiler house roof is closed before pressure parts are set. Each step ends with a named acceptance check; do not start the next step until it is signed.

  1. Unload and inspect. Check shock indicators on the drum and cyclone; record any refractory crack on the delivery note before the crane is released.
  2. Set the boiler on its plinth. Align anchor bolts to the template, grout in one pour, level at ±2 mm/m and ±5 mm overall, and mark the 1.5 m front, 1.0 m side and 1.2 m gun-swing clearances.
  3. Erect drum, headers and water walls. Set to drawing elevation, plumb walls to ±3 mm over full height, weld to the qualified procedure, and radiograph 10% of circumferential butt welds.
  4. Fit the air distributor and bubble caps. Confirm every cap hole is clear and cap height within ±2 mm of drawing.
  5. Install the loop seal and ash return leg. Check nozzle orientation and the return inlet gap before closing the access door.
  6. Lay refractory to the supplier anchor layout. Keep expansion joints free of mortar and cure at 25 °C/h to 600 °C with holds.
  7. Connect flue and air ducts. Set expansion joints at half cold travel, with no shear across the joint face.
  8. Pipe feed water, blowdown and safety valves. Slope drains at 1:100 to the pit and support the safety valve outlet independently.
  9. Install the bed gun and flame scanner. Set insertion depth to drawing, align the sight line on the flame root, and prove purge air.
  10. Loop-check instruments and interlocks. Simulate each trip at the terminal, not in software, and record it on the interlock sheet.
  11. Connect motors at the terminal boxes. Bump each fan for rotation, run 30 min uncoupled, and record vibration below 4.5 mm/s RMS.
  12. Charge bed material and run the cold fluidisation test. Plot bed pressure drop against primary air flow and match the calculated curve within ±10%.
  13. Hydrostatic test at 1.5 × design pressure for 30 min, then insulate and clad; casing surface ≤60 °C at 25 °C ambient.
Lifting and riggingThe drum and cyclone are not designed for slinging at the nozzles. Use the marked lifting lugs only, with a spreader beam, keeping the load clear of refractory-lined sections. Never lift the assembled boiler by ductwork or platform steel, and stop if wind exceeds 10 m/s at the hook.
Expansion and anchorsThis is a bottom-supported boiler: the pressure parts grow upward by 60–80 mm between cold and full load. Set slides and guides so drum and downcomers move freely, leave the calculated cold gap at every restraint, and never weld platform steel to moving parts: one brace transfers expansion into the water wall and cracks the first tube weld.

The bed gun is a service item, not a permanent fixture. Keep the manufacturer’s nozzle spanner and a spare swirl plate on site, and follow the start-up burner specification for oil or gas pressure at the gun.

4. Commissioning and handover

Hydrostatic test. Test at 1.5 times design pressure: 2.4 MPa for the 1.6 MPa units, 3.75 MPa for 2.5 MPa and 6.3 MPa for the 4.2 MPa design of the 3.82 MPa unit. Use water at ambient plus 5 °C and below 70 °C, fill from the bottom, vent every high point, and hold 30 min after stabilisation. Acceptance: no leak, no weeping at a welded seam, no permanent deformation. This follows GB/T 16508 and TSG G0001; third-party inspection is available on request and no other certification is implied.

Fill and vent. Fill through the economiser with the drum vents open until water runs clear, then close and bring the drum to normal level. Confirm the level responds within 30 s to a 10 mm gauge glass change before lighting the bed gun.

Bed gun set-up. Light on minimum fire with 30% primary air, then set combustion: O2 3–5% and CO2 11–13% at the gun outlet, CO below 50 ppm, stack 160–180 °C. Prove the scanner sees flame within 3 s and drops the gun within 1 s on simulated flame loss. Heat the bed at no more than 100 °C/h and hold at 600 °C through the refractory cure curve.

Interlock Simulated condition Expected result
Drum low water Level signal at −75 mm Fuel and secondary air trip, alarm, induced draught purge for 5 min
Drum high water Level signal at +75 mm Feed pump stops, alarm; fuel stays on until the level recovers
Furnace pressure high +1.5 kPa at the furnace outlet Induced draught fan to maximum, then master fuel trip at +2.5 kPa
Bed temperature high Thermocouple at 1 020 °C Coal feed stops, primary air stays on, alarm and trend capture
Primary air fan trip Contactor opened Master fuel trip, bed gun off, 5 min purge, no coal until air is restored
Bed gun flame failure Scanner signal lost Gun valve closes within 1 s, purge 30 s, alarm
Safety valve Pressure raised to set point Valve lifts at ≤ design pressure, accumulation ≤10%, reseats without simmer

Trial runs. Run 4 h each at 50%, 75% and 100% load, logging bed temperature, bed pressure drop, output, stack temperature and emissions every 15 min. Then run 24 h at the plant’s real load, including a shift change and one soot-blowing cycle. Acceptance: bed at 850–950 °C above 40% load, steam temperature within ±10 °C of set point, efficiency 88–91% on the design fuel.

Handover documents. Supply as-built drawings, material and welding records with radiographs, refractory cure record, cold fluidisation curve, interlock test sheets, safety valve certificates, the 4 h and 24 h logs, and this manual with the serial number entered. The efficiency and fuel consumption pages give the trial run reference figures.

5. Normal operation

Cold start. Charge bed material to the drawing height, typically 450–600 mm, and run the cold fluidisation check. Start the induced draught fan, purge 5 min at 30% air, light the bed gun, and raise bed temperature at 100 °C/h to 600 °C. Start coal at 550–650 °C with the gun supporting and hold 20–30% load until the bed is stable at 850 °C. Withdraw the gun, then raise load at 5% per minute at most. A cold start takes 6–10 h.

Hot standby. Keep the bed above 700 °C on minimum coal, 30% air and the gun at low fire where ash fusion allows. Restart within 30 min by restoring air, then coal. Below 600 °C treat the unit as a cold start: never force coal into a cooling bed, because unburnt fuel accumulates and can cause a pressure excursion on re-light.

Running log. Log every two hours against these bands at steady load.

Parameter Normal band Action if outside
Bed temperature 850–950 °C, target 900 °C Adjust coal or air; gun support below 800 °C
Bed pressure drop 7–10 kPa at rating, ±0.5 kPa stable Drain or add bed material; check bubble caps
Furnace outlet pressure −0.1 to −0.3 kPa Tune induced draught; check for a tube leak
Superheated steam temperature Set point ±10 °C Attemperator or soot blowing
O2 at economiser outlet 3–5% Trim secondary air; check air preheater leakage
Loop seal temperature 850–950 °C, within 20 °C of bed Check loop seal air and dipleg flow
Ash cooler outlet Below 200 °C Check water flow and ash discharge rate
Stack NOx / SO2 / dust NOx ≤50, SO2 ≤35, dust ≤10 mg/Nm3 Trim SNCR, limestone feed or bag cleaning

Normal shutdown. Reduce load at 5% per minute to 30%, stop coal and keep air on 5 min to burn out the bed. Stop the gun, then the primary air fan once the bed is below 400 °C. Cool at no more than 100 °C/h; never spray water on hot refractory.

Emergency shutdown. Trip on drum level below −75 mm, loss of both air fans, furnace pressure above +2.5 kPa, a confirmed tube leak, or fire in the ducting. Keep the induced draught fan on 5 min to purge, then isolate fuel, limestone and ash at the local isolator.

Lay-up over 30 days. Wet: fill with condensate or demineralised water at pH 10.5, add oxygen scavenger to 200 mg/L, circulate monthly. Dry: drain, dry with warm air, place desiccant in the drum, hold relative humidity below 30%. Seal access doors and keep rainwater out of bed and cyclone.

6. Maintenance schedule

The bed, cyclone and loop seal carry the wear. Every row has an acceptance figure; a row without a recorded value is not complete.

6.1 Daily (each shift)

Task What to check / acceptance Tool or reference Who
Bed pressure profile Five taps within ±0.5 kPa of the load baseline; no step above 1.0 kPa Inclined manometer, log sheet Operator
Bed temperature survey 850–950 °C; spread across the width ≤40 °C Calibrated thermocouples Operator
Furnace and cyclone draught Furnace outlet −0.1 to −0.3 kPa; cyclone inlet within design Panel gauge Operator
Loop seal and return leg 850–950 °C and no more than 20 °C above bed temperature Infrared thermometer Operator
Drum level and blowdown Level ±25 mm; blowdown to the conductivity target Sight glass, conductivity meter Operator
Limestone feed Ca/S 1.8–2.2; SO2 trend flat; silo above 30% Feeder dial, analyser Operator
Soot blowing Convection pass ΔP stable; blow only above 60% load Soot blower controller Operator
Ash discharge and stack No visible dust; ash cooler outlet below 200 °C Visual check, infrared thermometer Operator

6.2 Monthly

Task What to check / acceptance Tool or reference Who
Cyclone and loop seal internal check Cracks below 3 mm wide; no spall above 0.05 m2; anchors covered Access door, boroscope, steel rule Mechanical fitter
Bed pressure mapping Weekly full profile; monthly bed ΔP within ±10% of the design curve at 50, 75 and 100% Manometer set, baseline file Shift engineer
Air preheater leakage O2 rise across the preheater ≤1.5 percentage points Portable analyser Instrument technician
Safety valve check Manual lifting lever free; set pressure within ±3% Lifting gear, calibration record Shift engineer
Feeder calibration Coal and limestone within ±2% of set rate Weigh scale, stopwatch Instrument technician
Fan vibration and bearings ≤4.5 mm/s RMS; bearing temperature below 75 °C Vibration meter, contact probe Mechanical fitter

6.3 Quarterly / semi-annual

Task What to check / acceptance Tool or reference Who
Cyclone wear survey Refractory loss ≤5 mm since the last survey; no exposed anchors Depth gauge, photo grid Refractory contractor
Tube erosion shields Shield thickness ≥70% of 6 mm, replace at 4 mm Ultrasonic thickness gauge Boiler inspector
Expansion measurement Cold-to-hot movement within ±5 mm of calculated; slides free Dial gauge, reference marks Mechanical fitter
SNCR system Nozzle spray pattern even; NSR 1.2–1.8; urea concentration 20% Nozzle test rig, refractometer Commissioning engineer
Refractory crack and gap survey Cracks below 3 mm; expansion gaps clear of debris Feeler gauge, torch Refractory contractor
Instrument calibration Bed thermocouples, pressure taps and O2 analyser within ±1% of span Calibrator, certificate Instrument technician

6.4 Annual shutdown inspection

Task What to check / acceptance Tool or reference Who
Refractory thickness survey Grid at 500 × 500 mm; remaining ≥70% of 80 mm design, replace below 50 mm Depth gauge, survey drawing Refractory contractor
Tube thickness survey Water wall and superheater at 3-year interval; retire at 80% of nominal Ultrasonic gauge, thickness map Boiler inspector
Cyclone and loop seal rebuild Anchors sound, new refractory to the cure curve, gaps set cold Supplier procedure Refractory contractor
Safety valve overhaul Set pressure within ±3%, accumulation ≤10%, reseat clean Test bench, certificate Valve technician
Air preheater cleaning and leak test Gas-side ΔP back to design; no cross-leak above 5% Water wash, analyser Mechanical fitter
Fan overhaul Bearing clearance per supplier, impeller wear ≤3 mm, alignment ≤0.05 mm Micrometer, laser alignment Mechanical fitter
Drum internal inspection Separator vanes intact, no scale above 0.3 mm, chemical clean if exceeded Boroscope, scale sample Boiler inspector
Hydrostatic test after major repair 1.5 × design pressure, 30 min, no leak Test pump, calibrated gauge Shift engineer
RecordsKeep log sheets, thickness maps, interlock sheets and refractory surveys for three years, and the last two annual surveys as the wear-rate baseline. Escalate any measurement moving more than twice the previous year’s rate within one shift: a doubled wear rate is the earliest sign of a bed or air problem, long before a tube fails.

7. Troubleshooting

Read the bed pressure profile and temperature survey together before changing a set point.

Symptom Likely cause Check Remedy
Bed temperature falls below 800 °C Wet or low-grade fuel, excess air, limestone overfeed Feeder rate, fuel moisture, O2, limestone dial Support with the bed gun, cut excess air, restore coal quality
Bed temperature above 1 000 °C High calorific fuel, low air, low ash fusion Fuel certificate, air/fuel ratio, bed sample Increase air, reduce coal, drain agglomerated bed material
Bed pressure drop rises steadily Bed inventory growth, agglomerates, slag Pressure mapping, drained sample Increase ash extraction, drain bed, check fuel size
Bed pressure drop collapses Fan trip, blocked bubble caps, bed drain open Fan current, distributor ΔP, drain valve Restore air, re-fluidise; never feed coal to a defluidised bed
Loop seal temperature high or ash return stops Loop seal air low or blocked, dipleg plug Loop seal air 1.5–2% of total, dipleg ΔP Clear the blockage, restore air, then raise load
Stack dust above 10 mg/Nm3 Bag failure, cyclone efficiency loss Bag ΔP, opacity, cyclone survey Replace bags, repair cyclone refractory and dipleg seal
SO2 above limit at normal Ca/S Limestone quality or size, feed point blocked CaCO3 certificate, 0–1 mm screen, feeder Raise Ca/S to 2.2, correct size, clear the feed line
Drum level falls with rising make-up Tube leak in water wall or economiser Furnace pressure, acoustic check, feed flow balance Shut down, isolate, repair; do not chase the leak with make-up

8. Spare parts and service

Hold the following for the first year; double the wear items for a unit on high-ash gangue.

Pressure and bed

Bubble caps (10% of total), two bed thermocouples, drum level electrode set, lower-furnace erosion shields, access door gaskets.

Refractory

Two tonnes of cyclone and loop seal castable, 200 kg anchor steel, 20 m ceramic fibre blanket, curing compound.

Rotating and feed

One coal feeder belt, one limestone feeder screw, fan bearing set, coupling element, one set of air preheater gaskets.

Combustion and control

One bed gun nozzle and swirl plate, flame scanner, one set of analyser filters, spare pressure transmitter.

Consumables: limestone, bed sand, urea for SNCR, soot blower lane gaskets and the specified bearing grease. Order by model, serial number and drawing number, quoting the general arrangement item position. DHX and SHX units share the burner and instrument set; refractory shapes differ between the 2.5 MPa and 3.82 MPa cyclones.

Service: remote diagnosis within one working day, site attendance within three working days in the region, and a commissioning engineer for the annual inspection. Keep the manual library copy current and run any fuel change through the fuel and air calculator before it reaches the feeder.

9. Document control

Rev Date Change
A 2026-11 First issue for the DHX, SHX and QXX family
B 2026-11 Added SNCR checks and the 3-year tube thickness interval
C 2026-11 Refractory acceptance criteria revised to the 70% rule

This file is hash-verified. Compare the SHA-256 on the verification page with the handover certificate; if they differ, the copy is not the issued revision. Report discrepancies to Henan Yongxing Special Equipment Co., Ltd. before using it for maintenance decisions.

This manual covers the family. Your unit has its own serial number, fuel analysis and drawing set, and the site-specific manual carries those figures.

Request the site-specific manual with the boiler serial number and the fuel certificate.

Document control and download

Document

YX-MAN-CFB · revision 1.0 · issued 2026-11
Applies to the model families listed in section 1.

Download

Manual PDF · 238 KB
Print-ready A4, same content as this page.
Weekly maintenance log sheet · one page for the shift file.

SHA-256 163fa04407d39ee16829f9229a5b433d58133527b686b7447f54ef966a5c72c3

This fingerprint is calculated from the PDF file itself. Verify it on the verification page — the check runs in your browser, so an altered file cannot pass. A signed copy of the full manifest is published alongside it.

Key facts

  • YXBOILER is the global brand and manufacturing site of Henan Yongxing Boiler Manufacturing Co., Ltd., an industrial boiler and pressure-vessel manufacturer founded in 1981 in Henan, China.
  • Main products: steam boilers, hot-water boilers, thermal-oil heaters, biomass and coal-fired boilers, electric boilers, pressure vessels and autoclaves.
  • Serving customers in worldwide with selection, drawings, export packaging, installation guidance and spare parts.
  • Contact: WhatsApp +86 133 5377 2661 · [email protected].

Related on this site

Specifications, categories and further reading.

YXBOILER network

The same manufacturer, documented site by site.