الرئيسية / Burners, Softeners, Pumps & Control Cabinets — Installation, Commissioning & Maintenance Manual

Burners, Softeners, Pumps & Control Cabinets — Installation, Commissioning & Maintenance Manual

This manual covers the boiler-house auxiliaries supplied with YXBOILER packaged plants: gas, light-oil and dual-fuel burners from 0.5 to 20 MW, water softening plants, feed water and circulating pumps, control cabinets with PLC panels, and steam headers and distributors. It is written for the site engineer, commissioning technician and maintenance fitter who position, connect, adjust and service these items. Each section gives installation clearances, connection requirements, commissioning checks and maintenance rows with numeric acceptance values.

Document YX-MAN-AUXRevision 1.0Issue date 2026-11Applies to Burners, softeners, pumps, control cabinets, headersLanguage English

1. Scope and model coverage

Model or equipment line Capacity range Design pressure, temperature Fuel or medium Typical duty
YX-G gas burner train 0.5–20 MW Furnace −20 to −50 Pa; ambient 0–50 °C Natural gas, LPG Single or dual boiler package
YX-O light-oil burner 0.5–14 MW As above Light diesel, 3–6 cSt at 20 °C Sites without a gas supply
YX-DF dual-fuel burner 1–20 MW As above Gas and light oil Interruptible gas contracts
YX-SF water softener 2–50 t/h 0.6 MPa, 5–45 °C Raw water, hardness ≤ 450 mg/L Make-up for 1–20 t/h boilers
YX-FP feed pump, YX-CP circulating pump 2–60 m³/h 1.6 MPa, 105 °C Treated water Boiler feed and hot-water loop
YX-CC control cabinet, PLC panel Burner load up to 20 MW 400 V, IP54, 0–50 °C ambient — Boiler and burner control
Steam header and distributor DN80–DN400 1.6 MPa, 204 °C Saturated steam Multi-boiler distribution

The scope ends at the terminal box, the burner gas flange and the header outlet flange. Excluded are the gas yard upstream of the manual isolation valve, fuel storage tanks and their bunding, chimney steel, civil works, and site electrical distribution beyond the cabinet. Burner capacity selection and the matching boiler are covered in the separate boiler manual and in the capacity selection pages; the full document set is listed in the manual library.

2. Site and utility requirements before delivery

Confirm every item below before the equipment leaves the factory. Missing clearances or a soft water supply are the two most common causes of delayed commissioning. Send the completed utility schedule with the order acknowledgement so the burner train and softener are set for site conditions.

Item Requirement Tolerance or note
Foundation and plinth Concrete plinth 150 mm above floor, cured 28 days Level ±2 mm/m; non-shrink grout 25 mm
Burner swing and tube access Door swing plus 0.5 m clear; 1.2 m at hinge side Rear tube removal per boiler manual
Softener access 0.8 m at valve face, 1.2 m headroom at resin port Brine tank within 3 m of ejector
Pump access 0.8 m at non-drive end Seal and bearing withdrawal
Boiler house ventilation 3 air changes/h plus combustion air Non-closing louvres; 1.3 m³ air per m³ gas
Feed water quality Hardness ≤0.03 mmol/L, pH 10–12, oxygen ≤0.1 mg/L Deaerator when output exceeds 6 t/h; conductivity ≤3000 µS/cm at 1.0 MPa
Fuel supply Gas 20–50 kPa; oil 0.3–0.6 MPa at train inlet Stable within ±10%; no water or solids
Flue and chimney Draught −20 to −50 Pa at furnace outlet Stack height and materials to local code
Electrical supply and earthing 400 V ±10%, three-phase, 50 Hz; earth ≤4 Ω PLC signal earth separate, ≤1 Ω
Drainage and blowdown pit Pit sized for 10% of maximum evaporation Discharge cooled to ≤60 °C

3. Installation sequence

  1. Unload and inspect. Check the packing list against the general arrangement drawing and confirm flange caps and blind plates are fitted. Photograph any impact damage before signing and record burner, pump and softener serial numbers.
  2. Position the softener skid. Set it on the plinth with 0.8 m clear at the valve face and 1.2 m headroom at the resin port, level to ±2 mm/m, and anchor all four feet. Confirm the brine tank sits within 3 m of the ejector.
  3. Grout the pump baseplates. Clean the concrete, shim to level and pour non-shrink grout; allow 24 h before tightening. The shaft must turn freely by hand with the coupling removed.
  4. Fit the burner. Renew the furnace flange gasket, enter the burner tube square and tighten diagonally in three passes. Check that the burner door swings through its full arc without touching insulation or pipework.
  5. Assemble the gas train. Install strainer, regulator, safety shut-off valves, leak-test valve and pressure switches in the drawing order, each pipe run independently supported. No pipe strain may remain on the burner flange.
  6. Connect the oil line. Mount the oil pump, filter and heater on a supported frame, slope suction piping back to the tank and bleed all high points. Pressure-test the line at 1.5 × pump pressure for 10 min.
  7. Pull the electrical cables. Separate power and signal trays by 200 mm, gland every entry and terminate to the numbered schedule. Check earth continuity from the cabinet to each skid before energising.
  8. Connect instrument air. Supply dry air at 0.4–0.6 MPa through a filter regulator and set 0.4 MPa at the burner control valves.
  9. Erect the steam header. Set anchors and sliding shoes, fit the expansion joint at the stated cold pull and slope 1:200 towards the traps. Never spring the header to close a flange gap.
  10. Flush the water side. Bypass the softener, flush new pipework to drain until the water runs clear, then refit strainers. Never flush through the resin bed.
  11. Pressure-test the header. Test at 1.5 × design pressure for 30 min; there must be no visible leak and no gauge pressure drop.
  12. Commission the softener. Backwash, regenerate, rinse and test outlet hardness; repeat the cycle until hardness is ≤0.03 mmol/L.
  13. Insulate the header. Apply insulation only after a successful test; surface temperature must remain below 50 °C in service.
Lifting and riggingBurner fan sections, softener vessels and pump sets have marked lifting points. Use certified slings and shackles, never lift by the gas train, piping or terminal box, and keep personnel clear of suspended loads. Lower softener vessels slowly; resin and water weight can exceed the dry weight by 40%.
Expansion and anchor pointsThe header fixed point carries the full thermal thrust. Sliding shoes must move freely and the expansion joint must never be compressed to make a flange fit. Where the drawing shows a flexible connection at the burner, keep it free of torsional load.

4. Commissioning and handover

Hydro-test the header and softener vessels at 1.5 × design pressure, held for 30 min, following GB/T 16508 and TSG G0001 practice. A 0.6 MPa softener vessel is therefore tested at 0.9 MPa; the pump casing is tested by the maker and is not re-tested on site. Fill the system through the highest connection at no more than 0.2 MPa/min, venting the header and pump casing as water rises, and confirm all air vents are closed before pressure is raised.

Burner commissioning starts with the gas train leak test, then low-fire adjustment, then high fire. Set combustion with a calibrated analyser at low, mid and high fire and record every point. The target bands below apply to burners from 0.5 to 20 MW; the burner range pages give the model-specific nozzle and cam data.

  1. Close the manual isolation valve and the burner gas valve, then vent the train to atmosphere through the test point.
  2. Pressurise the train with air or nitrogen to 1.1 × maximum working pressure. A train working at 50 kPa is tested at 55 kPa.
  3. Close the test valve, allow 1 min for stabilisation, then record the starting pressure.
  4. Hold for 5 min. No pressure decay is acceptable; any fall indicates a seat, diaphragm or joint leak.
  5. Bubble-test every joint and valve seat with an approved detector. Repair the fault and repeat the full 5 min test from step 2.
  6. Reconnect, purge the train with fuel gas to the vent until the gas reading is stable, then check the purge point for leaks.
Leak test safetyTest with air or nitrogen, never with a flame. Post the test pressure and result on the commissioning sheet, and repeat the test after any gas train joint is broken.
Combustion parameter at high fire Gas firing Light-oil firing
Oxygen, O2 3–5% 4–6%
Carbon monoxide, CO <50 ppm <50 ppm
Excess air 15–25% 20–35%
Stack temperature 140–170 °C 170–200 °C
Carbon dioxide, CO2 9.5–10.5% 11–12.5%
Flame scanner signal 60–100%; flame-off <10% 60–100%; flame-off <10%

On oil firing, set the electrode gap to 2.5–3.5 mm, keep the nozzle face flush to 2 mm proud of the diffuser, and set oil pump pressure to 1.2–1.6 MPa with filter differential below 0.05 MPa. Replace a nozzle that has been cleaned twice; eroded orifices cannot be restored by wire brushing. Record stack temperature at each load step as the baseline for later trend checks.

Prove every safety interlock by simulation before handover, using the test column, test valves and simulator points. Record the actual trip time and the reset action.

Interlock Simulated condition Expected result
Low water level Lower the test column electrode or float Burner trips within 5 s, alarm sounds, restart blocked until reset
Flame failure Close the manual cock for 3 s Fuel valves close within 1 s, lockout, post-purge 60 s
Gas pressure low or high Open or close the pressure switch test valve Trip at setpoint, repeatability within ±5%
Combustion air low Throttle the air switch impulse line Trip before the fuel valve opens
High stack temperature Simulate 30 °C above setpoint Alarm at first stage, trip at second stage
Emergency stop Press the mushroom head All fuel valves close, fan stops, alarm latches
Boiler limit control Lower the pressure or temperature setpoint Burner stops at setpoint and restarts on demand

Run a 4 h trial at 50–100% load, logging hourly, then a 24 h continuous run at site load. Handover documents are the general arrangement drawing, wiring diagram, gas train drawing, pressure test certificates, interlock test record, combustion report, softener commissioning sheet, this manual and the spare parts list.

5. Normal operation

Start-up from cold. Confirm softener outlet hardness and brine tank level, open the feed pump suction valve and start the feed pump with discharge set 0.2 MPa above boiler pressure. Start the fan, open the damper to 25% and purge for 60 s. Prove the flame scanner, light the burner at low fire and confirm the flame signal exceeds 60%. Raise load in 10% steps every 5 min, watching O2, CO and stack temperature. Bring the header to setpoint, then open the main stop valve slowly with all traps draining.

Start-up from hot standby. Keep the header warm at 0.3–0.5 MPa with traps open and the burner cycling on low fire. Before restarting, purge for 60 s, check that the scanner sees no flame, and confirm the drum level is between the normal water level marks. Do not bank the burner with fuel in the furnace.

Parameter Normal band Check frequency
Header pressure 1.0 ± 0.05 MPa Hourly
Burner O2 3–5% gas, 4–6% oil Each shift
Stack temperature Baseline +30 °C maximum Hourly
Flame signal >60%, steady Each shift
Pump discharge pressure 1.2–1.4 MPa Hourly
Pump bearing temperature <70 °C Each shift
Softener outlet hardness ≤0.03 mmol/L Daily
Cabinet internal temperature <40 °C and <15 K above ambient Daily
Steam trap discharge Intermittent, no live steam Daily

Normal shutdown. Reduce load to low fire, run for 5 min to purge the furnace, stop the burner and allow the 60 s post-purge before stopping the fan. Close the main stop valve, drain the traps and keep the feed pump running until the level is stable. Emergency shutdown. Press the emergency stop, close the main stop valve and do not restart until the cause is found and the interlock circuit is proved.

Lay-up over 30 days. For wet lay-up, drain and refill with treated water at pH 10–12, add oxygen scavenger and circulate weekly. For dry lay-up, drain completely, dry the interior with warm air and place desiccant in the header; seal all openings and record the date. Softener resin stays wet; keep the brine tank covered and regenerate monthly.

6. Maintenance schedule

The four schedules below cover every auxiliary in this manual; model-specific service data for the water softening plant, feed water pumps and control cabinet is published with each model. A task is complete only when the measured value is written on the log sheet with the date and initials. Vibration readings are compared with the ISO 10816 zone A/B limits for the machine class.

6.1 Daily, each shift

Task What to check and acceptance Tool or reference Who
Softener outlet hardness ≤0.03 mmol/L; regenerate immediately if above Titration kit Shift operator
Brine tank Salt at least 200 mm above the grid, no crust or bridging Visual dip Shift operator
Feed and circulating pumps Bearing <70 °C, vibration ≤4.5 mm/s, seal leak ≤5 drops/min IR thermometer, vibration pen Shift operator
Burner flame Signal >60%, stable, no pulsation or roar Panel display Shift operator
Combustion readings O2, CO and stack temperature inside the section 4 bands Flue gas analyser Shift operator
Control cabinet No alarm, fans running, filter clean, internal <40 °C Visual, thermometer Shift operator
Steam header traps Intermittent discharge, no continuous live steam Listening rod, IR Shift operator
Gas train Inlet 20–50 kPa, no smell, joints tight Manometer, detector Shift operator
Oil system Pressure 1.2–1.6 MPa, filter differential <0.05 MPa Gauges Shift operator

6.2 Monthly

Task What to check and acceptance Tool or reference Who
Burner nozzle and electrodes Clean, no carbon; electrode gap 2.5–3.5 mm; nozzle not eroded Feeler gauge, nozzle gauge Fitter
Flame scanner Lens clean, signal >60%, flame-off <10% Lint-free cloth, panel Fitter
Gas train valve tightness No bubble at any seat or joint over 1 min Leak detector Fitter
Pump coupling alignment Offset ≤0.05 mm, angular ≤0.05 mm per 100 mm Dial gauge or laser Fitter
Softener backwash Bed expansion 50–70%, no resin carry-over Sight glass, flow meter Fitter
Cabinet thermal scan No hot spot more than 15 K above ambient IR camera Electrician
Terminal torque check M4 1.2 N·m, M6 4.5 N·m, or drawing value Torque wrench Electrician
Header insulation Surface <50 °C, no gaps at flanges or supports IR thermometer Fitter
Strainers Pump suction and trap strainers clean, no perforation Spanner, light Fitter

6.3 Quarterly or semi-annual

Task What to check and acceptance Tool or reference Who
Full gas train leak test 1.1 × working pressure, 5 min hold, no decay Test kit, calibrated gauge Fitter and electrician
Combustion re-check All points inside section 4 bands; analyser zeroed Flue gas analyser Commissioning technician
Pump seal and bearings Seal faces clean, grease per schedule, bearing <70 °C Hand tools, grease gun Fitter
Softener capacity test Measured capacity ≥80% of design; resin sample examined Test kit, sample jar Service technician
Earth continuity and insulation ≤0.1 Ω to each skid; >1 MΩ at 500 V Earth tester, megger Electrician
Sensor calibration Pressure transmitter ±0.5% FS, RTD ±1 °C, level electrode trips at the marked level Calibrator, test column Instrument technician
Steam trap overhaul Replace any trap passing live steam; renew gaskets Trap spares Fitter

6.4 Annual shutdown inspection

Task What to check and acceptance Tool or reference Who
Burner overhaul Nozzle, electrodes, diffuser and fan bearings renewed as needed; leak test after assembly Burner kit, drawing Service technician
Gas train valve overhaul Seats, diaphragms and springs replaced; set pressures verified Valve kit, pressure gauge Service technician
Pump overhaul Bearings and seal renewed; wear ring clearance ≤0.3 mm Pump kit, feeler gauge Fitter
Softener resin and valves Resin replaced if capacity <80%; lining sound; valve seats renewed Resin, valve kit Service technician
PLC battery and cabinet Battery >2.8 V, replace every 3–5 years; contactors clean; all terminals torqued Multimeter, torque wrench Electrician
Safety and relief valves Set pressure ≤ design, accumulation ≤10%, clean reseat Test bench Authorised test house
Header inspection Supports, expansion joint, insulation and wall thickness at bends UT gauge, visual Inspector
Instrument loop check Sensor to PLC, alarm and trip proved end to end Loop simulator Instrument technician
RecordsRetain log sheets for three years. Any reading outside the stated band is an anomaly: record it, tag the equipment and escalate to the site engineer the same shift. Do not adjust a safety device to clear an alarm.

7. Troubleshooting

Symptom Likely cause Check Remedy
Burner locks out at start No flame signal, air in gas line, wrong electrode gap Scanner display, purge, gap Purge longer, reset gap to 2.5–3.5 mm
Flame signal falls during run Dirty scanner lens, unstable fuel pressure, wrong nozzle Lens, inlet pressure, nozzle size Clean lens, stabilise pressure, fit correct nozzle
CO above 50 ppm Insufficient air, carboned nozzle, diffuser set too deep O2, nozzle, diffuser position Clean nozzle, reset combustion to section 4
Stack temperature rising Excess air or fouled heating surface O2 trend, boiler baseline Reset air, clean boiler tubes
Softener hardness breakthrough Resin exhausted, brine failure, channelling Brine level, salt dose, backwash flow Regenerate, inspect and clean resin bed
Softener pressure drop high Fouled bed, blocked strainer Inlet and outlet gauges, strainer Backwash, clean strainer, replace resin if compacted
Pump vibration Misalignment, cavitation, worn bearing Alignment, suction pressure, bearing sound Realign, raise suction head, replace bearing
Mechanical seal leak Dry running, no flush, worn faces Flush flow, seal area Restore flush, replace seal
Cabinet over temperature Fan failed, filter blocked, high ambient Fan, filter, thermal scan Replace fan, clean filter, shade the cabinet
Steam trap passing steam Failed trap, dirt on seat Ultrasonic or IR check Replace trap, blow down strainer

8. Spare parts and service

Hold the following first-year spares on site. Items marked as consumables should be replaced at the interval shown rather than stocked indefinitely.

  • Burner: two nozzle sets, two electrode pairs, one flame scanner, two flange gasket sets, one fan bearing set, one gas train diaphragm and spring set, four filter elements.
  • Softener: resin for 10% of bed volume, one brine valve repair kit, one ejector, gasket set, hardness test reagents.
  • Pumps: two mechanical seals, two bearing sets, two coupling elements, gasket set.
  • Cabinet: two PLC batteries, one contactor coil, fuse set, four filter mats, one spare pressure transmitter and one RTD.
  • Header: two steam traps, gasket set, one insulation section per 10 m.

Order by model, serial number and drawing number, quoting the item position on the drawing. Consumables are the nozzle, electrodes, filter elements, resin, seals, gaskets and PLC battery. Service response is one working day for acknowledgement and a site visit within five working days for a stoppage; emergency cover is quoted separately. Contact the service desk through the contact page with the serial number and a photograph of the nameplate.

9. Document control

Revision Date Change
1.0 2026-11 First issue for the auxiliary equipment family.

This file is hash-verified. The SHA-256 digest of the published PDF is listed on the verification page, and any printed copy is uncontrolled unless the digest matches. Check the digest shown at the manual verification page before using this document for commissioning or maintenance. Report any mismatch to Henan Yongxing Special Equipment Co., Ltd..

Need the site-specific manual with your burner, softener, pump and cabinet serial numbers, factory setpoints and wiring schedule? Send the nameplate photograph and order number through the contact form.

Request the site-specific auxiliary manual

Document control and download

Document

YX-MAN-AUX · revision 1.0 · issued 2026-11
Applies to the model families listed in section 1.

Download

Manual PDF · 249 KB
Print-ready A4, same content as this page.
Weekly maintenance log sheet · one page for the shift file.

SHA-256 9fc2becc2d03e3897361c758260a43cc72edf4ff9d501383323e9c4bc1adc010

This fingerprint is calculated from the PDF file itself. Verify it on the verification page — the check runs in your browser, so an altered file cannot pass. A signed copy of the full manifest is published alongside it.

Key facts

  • YXBOILER is the global brand and manufacturing site of Henan Yongxing Boiler Manufacturing Co., Ltd., an industrial boiler and pressure-vessel manufacturer founded in 1981 in Henan, China.
  • Main products: steam boilers, hot-water boilers, thermal-oil heaters, biomass and coal-fired boilers, electric boilers, pressure vessels and autoclaves.
  • Serving customers in worldwide with selection, drawings, export packaging, installation guidance and spare parts.
  • Contact: WhatsApp +86 133 5377 2661 · [email protected].

Related on this site

Specifications, categories and further reading.

YXBOILER network

The same manufacturer, documented site by site.