This manual covers the safe operation and maintenance of Henan Yongxing Special Equipment Co., Ltd. electric steam boilers, electric hot-water boilers and electrode steam generators of the WDR, LDR, CLDR and ZWDR families. It is written for boiler operators, maintenance electricians and plant engineers who take responsibility for the unit after handover. It sets out site requirements, installation, commissioning, normal running, the electrical-safety maintenance schedule and fault finding. Where the element datasheet or the certified drawing supplied with a particular unit differs from this text, the unit-specific document takes precedence.
1. Scope and model coverage
All models use immersion resistance elements, or electrodes passing current through the boiler water on the ZWDR range. There is no burner, fuel train, flue or stack loss, hence 98–99% thermal efficiency. Heat is made inside the shell, so electrical protection, element condition and water quality replace combustion tuning as the maintenance focus.
| Model | Capacity | Design pressure / temperature | Heat source | Typical duty |
|---|---|---|---|---|
| WDR0.5-0.7 | 0.5 t/h (350 kW) | 0.7 MPa, 170 °C saturated | Resistance elements, 400 V | Laundry, small food plant, sterilising |
| WDR1-1.0 | 1 t/h (700 kW) | 1.0 MPa, 184 °C | Resistance elements, 400 V | CIP supply, hospital, dairy |
| WDR2-1.25 | 2 t/h (1.4 MW) | 1.25 MPa, 193 °C | Resistance elements, 400 V | Pharmaceutical, beverage, autoclave bank |
| WDR4-1.25 | 4 t/h (2.8 MW) | 1.25 MPa, 193 °C | Resistance elements, 400/690 V | Process plant, campus standby |
| WDR6-1.6 | 6 t/h (4.2 MW) | 1.6 MPa, 204 °C | Resistance elements, 690 V | Continuous process steam |
| WDR10-1.6 | 10 t/h (7.0 MW) | 1.6 MPa, 204 °C | Resistance or electrode, 6–10 kV | Large plant, grid balancing |
| LDR0.3-0.7 / CLDR0.35-95/70 | 0.3–0.35 MW hot water | 0.7 MPa; atmospheric, 95/70 °C | Resistance elements, 400 V | Space heating, domestic hot water |
| ZWDR1.4-1.0 | 2 t/h (1.4 MW) | 1.0 MPa, 184 °C | Electrode, 6 kV or 10 kV | Load following, renewable balancing |
Excluded from this manual: the incoming transformer and site electrical works upstream of the boiler isolator, cable tray outside the skid, softener installation pipework, structural steel and the process plant fed by the boiler. Induction and electromagnetic units follow the same schedule with their coil cooling circuit added at the annual inspection. For capacity and steam-load matching, see the capacity selection guide and the electric boiler range.
2. Site and utility requirements before delivery
An electric boiler needs less space than a fuel-fired unit but more electrical discipline. Confirm the following before dispatch: a crowded room blocks element withdrawal and a marginal supply causes nuisance trips.
| Item | Requirement | Tolerance / notes |
|---|---|---|
| Foundation or plinth | Reinforced concrete, 150 mm above floor, level and cured | Level within ±3 mm per metre; grout after alignment |
| Element-head clearance | Element bundle length plus 500 mm of free space | For bundle withdrawal, descaling and replacement |
| Side and rear clearance | 800 mm to walls; 1,000 mm in front of the control panel | Panel door must open to its full swing |
| Boiler house ventilation | About 3 m³/h per kW, outside air, no recirculation | Holds the room ≤40 °C at a 10 K rise |
| Feed water | Hardness ≤0.03 mmol/L, pH 8.5–9.5, dissolved oxygen ≤0.1 mg/L | Softener sized for peak make-up plus 20% |
| Boiler water | pH 10–12; conductivity ≤4,000 µS/cm at 1.0 MPa, ≤3,000 µS/cm at 1.6 MPa | Blowdown rate fixed at commissioning |
| Electrical supply | 400 V ±5%, 50 Hz, three-phase with neutral and PE | Voltage imbalance ≤2%; current imbalance ≤10% |
| Cable and breaker | Cable rated ≥1.25 × full-load current; breaker 1.15–1.25 × FLC | Voltage drop ≤3% at the terminal box |
| Earthing | PE conductor to shell, panel and pipework | Earth resistance <4 Ω, measured and recorded |
| Drainage and blowdown pit | At least 1 m³, with cooling before discharge | Blowdown water below 60 °C at the outlet |
| Ambient conditions | 5–40 °C, relative humidity ≤85%, non-condensing | Fit a panel heater where frost is possible |
A 700 kW unit on 400 V draws about 1,010 A full load, so the feed is a busbar or parallel-cable installation, not a small single feeder. Confirm transformer spare capacity before ordering. Demand charges usually decide the operating pattern more than the boiler does; the energy consumption notes explain how to read them together. For site energy management see ISO 50001; for electric process heat benchmarks, the US Department of Energy pages are a useful reference.
3. Installation sequence
- Unload on the lifting lugs only, set the unit on the plinth and check the nameplate against the order. Acceptance: element head and terminal box undistorted, no impact damage.
- Level on packers and grout the saddles. Acceptance: no rocking, level within ±3 mm per metre in both directions.
- Bond the shell to earth before any other connection. Acceptance: below 4 Ω on a fall-of-potential test.
- Connect feed water, main steam, safety valve, drain and blowdown branches. Acceptance: non-return arrows match flow, each branch supported independently of the shell.
- Fit the safety valve direct on its nozzle with no isolating valve between boiler and valve. Acceptance: lever free, set pressure stamped and not above design pressure.
- Fill with softened water and vent the shell. Acceptance: steady level in the gauge glass, vents closed only after water appears.
- Megger the element bank before first energising. Acceptance: at least 50 MΩ at 500 V DC with the terminal links removed.
- Terminate the power cables and torque the lugs to the section 6.2 values; check phase sequence and gland tightness. Acceptance: clockwise L1-L2-L3 on a rotation meter.
- Check the panel against the drawing: breaker rating, fuses, step outputs, transmitter ranges. Acceptance: every core numbered and matching the schematic.
- Hydraulic test at 1.5 times design pressure for 30 minutes. Acceptance: no leak at any joint, no pressure drop beyond gauge error.
- Flush the feed line, refill and commission the softener. Acceptance: outlet hardness ≤0.03 mmol/L, no resin carry-over.
- Function-test the interlocks with elements isolated, then start on stage 1 and raise load step by step. Acceptance: every simulated fault trips and latches, phase current within 10% of rated.
- Pressure-test and blow through the steam line to the plant. Acceptance: no weep at flanges after cooling, clean steam at the first sample point.
Never lift by the element head, terminal box or panel; the shell is top-heavy. Use certified slings on the four lifting lugs, keep a 3 m exclusion zone and never stand under a suspended load. On WDR6 and WDR10 the element head alone weighs more than 400 kg and needs a lifting beam for withdrawal.
Anchor at the fixed saddle only and let the other saddle slide. Connect the steam line through an expansion loop or braided flexible section; never use the shell as a pipe anchor. Carbon steel grows about 1.2 mm per metre between 20 °C and 184 °C, so a restrained 12 m run will crack a nozzle weld.
4. Commissioning and handover
Commissioning has three parts: mechanical and electrical checks, a hydrostatic test, and a witnessed interlock and load test. Work in that order and record every reading; these become the maintenance baseline. Before energising, megger each element group at 500 V DC, fill and vent, confirm the low-water cut-out is in circuit and set the step controller to zero output.
Hydrostatic test pressure is 1.5 times design — 1.05 MPa for a 0.7 MPa shell, 1.5 MPa at 1.0 MPa, 1.875 MPa at 1.25 MPa, 2.4 MPa at 1.6 MPa. Hold 30 minutes after stabilisation with the safety valve blanked and the element head in place. Acceptance: no leak, no permanent deformation, no pressure loss beyond gauge error. Testing follows GB/T 16508 and TSG G0001 practice; third-party inspection is available on request.
Run the interlock tests with the main breaker open and elements isolated, using the test keys or a simulated signal.
| Interlock | Simulated condition | Expected result |
|---|---|---|
| Low-water cut-out | Open the test valve or lower the float chamber until the level falls below the cut-out line | All element stages trip within 5 s, alarm sounds, reset is manual only |
| High-water alarm | Raise the level above the high-level mark | Alarm at the high mark, feed pump stops, elements continue |
| High-pressure limiter | Lower the set point 0.1 MPa below the safety valve setting and raise pressure | Elements trip at the set point; the safety valve must not lift |
| Over-temperature cut-out | Lower the outlet limit set point or use the test key | Trip before the outlet exceeds design temperature by 10 K |
| Safety valve | Raise pressure with stages on and the outlet closed | Lifts at or below design pressure; accumulation ≤10% of set pressure |
| Earth-fault relay | Inject test current at the relay rated residual current | Trips within 0.3 s; no reclose without manual reset |
| Phase failure / under-voltage | Open one phase at the isolator, then attempt a start | Start inhibited; phase-failure relay flags the lost phase |
| Panel access interlock | Attempt to close the isolator with the panel door open | Isolator cannot be closed, or the main contactor drops |
| Emergency stop | Press the E-stop button | All stages off within 1 s, alarm latched, manual reset required |
The 4-hour trial proves the unit; the 24-hour run proves the site. Record pressure, level, feedwater temperature, current per phase, panel temperature and make-up water every 30 minutes for 4 hours, then every 2 hours. Acceptance for both: no unplanned trip, imbalance below 10%, insulation resistance unchanged, make-up water below 2% of evaporation. Hand over the O&M manual, P&ID, schematics, element datasheet, hydro and interlock certificates, water treatment report, spares list, training record and declaration of conformity.
5. Normal operation
Start-up from cold. Check the level and the softener, then crack the main steam stop valve to warm the line. Close the isolator, release the E-stop and reset any latched interlock. Start the feed pump and confirm the level holds. Enable stage 1 and let the controller call for stage 2; on a cold shell the first stage may run for minutes before pressure moves. Watch the ammeter during the first 10 minutes — a cracked sheath shows as a current imbalance long before it trips.
Start-up from hot standby. A unit held 0.2–0.3 MPa below set point needs no warm-up. Confirm the level, release the standby lockout and let the controller restore stages in sequence. Never enable all stages at once; the inrush is exactly what the step-loading logic exists to prevent.
Running log. Log these each shift; two consecutive readings outside the band are an anomaly, not a rounding error.
- Steam pressure: set point ±0.05 MPa.
- Steam temperature: within 5 K of saturation temperature at the logged pressure.
- Feedwater temperature: 20–105 °C, steady.
- Current per phase: within 10% of rated, and within 10% of each other.
- Boiler water conductivity: ≤4,000 µS/cm at 1.0 MPa, ≤3,000 µS/cm at 1.6 MPa.
- Feedwater hardness: ≤0.03 mmol/L after the softener.
- Panel internal temperature: ≤ ambient + 10 K, never above 50 °C.
- Casing surface temperature: ≤45 °C; terminal box ≤ ambient + 15 K.
- Earth-leakage standing current: below 30% of the relay setting.
Normal shutdown. Reduce the set point in steps so the controller drops stages in reverse order, stop the feed pump at normal level and close the main steam stop valve. Isolate and lock off, and record the level. Do not open the element head until the shell is below 60 °C.
Emergency shutdown. Press the E-stop, close the main steam stop valve and open the isolator. Do not restore the level if the low-water cut-out has operated — a dry element bank may be above 400 °C and cold water can split the sheath. Megger the elements and record the event before any restart.
Lay-up over 30 days. Wet lay-up: drain, flush, refill with deaerated water at pH 10–12 plus oxygen scavenger, blanket with nitrogen at 0.02–0.05 MPa and circulate monthly. Dry lay-up: drain, dry the interior, place 1 kg of silica gel per m³ of shell volume in trays and blank all connections. On electrode units always drain and dry the electrode chamber; standing water drifts in conductivity and the unit will not load correctly on restart.
6. Maintenance schedule
Every task below starts with: isolate, lock off, tag, prove dead and discharge the element circuit. No panel door is opened on load. Intervals assume ≤0.03 mmol/L hardness and a single-shift plant; on hard water with three shifts, move every water-side interval up one band.
6.1 Daily (each shift)
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Log running parameters | Pressure, temperature, level and current within the bands in section 5 | Panel instruments, shift log | Operator |
| Blow down the gauge glass and level column | Returns quickly and settles at the same level; no blockage | Drain valve, sight glass | Operator |
| Bottom blowdown by conductivity | Conductivity back within limit; blowdown valve closes tight, no passing | Conductivity meter, blowdown valve | Operator |
| Read current on all three phases | Within 10% of rated and of each other | Panel ammeter or clamp meter | Operator |
| Check feedwater hardness | ≤0.03 mmol/L; softener in service, brine tank charged | Hardness test kit | Operator |
| Walk the panel and terminal box; read the event log | No hot-insulation smell, no discoloured terminals, fan running, filters clear, no unexplained trip | Visual, infra-red thermometer, HMI log | Operator |
| Check feed pumps and standby changeover | Starts on low level; no abnormal noise or leak | Test switch, ear | Operator |
6.2 Monthly
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Element insulation resistance test | ≥1 MΩ at 500 V DC per group, links removed, shell drained below the head | 500 V insulation tester | Electrician |
| Contactor inspection | Erosion below 1 mm, no silver migration or arcing tracks, arc chutes clean | Visual, contact gauge | Electrician |
| Thermal scan of power terminations | Terminals ≤65 °C, phase-to-phase difference ≤10 K, no hot joint | Infra-red camera under load | Electrician |
| Torque check of element terminals | M8 12 N·m, M10 24 N·m, M12 42 N·m; no loose or bright strand | Calibrated torque wrench | Electrician |
| SCR or power controller check (if fitted) | Heatsink below 70 °C, fan free, no gate fault, output balanced across phases | Clamp meter, controller diagnostics | Electrician |
| Low-water cut-out test | Trips within 5 s when the chamber is drained; manual reset only | Chamber drain valve | Operator and electrician |
| Safety valve manual lift | Lever lifts freely and reseats without weeping | Lifting lever, hearing and sight | Operator |
| Water quality review | Hardness and conductivity trends flat; blowdown rate still adequate | Log review, test kit | Plant engineer |
6.3 Quarterly / semi-annual
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Scale inspection on the element bundle | Scale below 0.2 mm; clean at 0.5 mm; replace the set above 1 mm | Bundle withdrawal, scale gauge | Maintenance fitter |
| Earth continuity and resistance | PE and all bonded parts continuous; earth resistance <4 Ω | Earth tester, continuity meter | Electrician |
| Earth-leakage relay trip test | Trips at rated residual current within 0.3 s, both settings if adjustable | Relay test key or injection set | Electrician |
| Breaker and isolator inspection | No contact pitting, mechanism free, incoming lugs at panel torque | Torque wrench, visual | Electrician |
| Pressure gauge and transmitter calibration | Gauge within 1.6% of span against a master; transmitter repeatable within 1% at three points | Master gauge, hand pump | Instrument technician |
| Step-load and maximum-demand review | Stages sequence correctly; peak demand within the contracted maximum; tariff windows respected | Panel trend, utility bill | Plant engineer |
6.4 Annual shutdown inspection
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Internal inspection of shell and element head | No pitting below 90% of wall thickness, no sludge, gasket faces clean | Borescope, ultrasonic thickness gauge | Inspector |
| Hydrostatic test | 1.5 × design pressure held 30 min, no leak or permanent deformation | Test pump, calibrated gauge | Inspector |
| Element replacement or descale | Insulation ≥1 MΩ, scale below 0.2 mm, new flange gasket and head insulation; torque per section 6.2 | Element kit, torque wrench, megger | Electrician |
| Safety valve set-pressure test | Lifts at or below design pressure, reseats tight, lead seal fitted | Bench test rig, certificate | Valve technician |
| Full interlock retest | All nine tests in section 4 pass with the elements isolated | Commissioning sheet | Commissioning engineer |
| Power connection re-torque | Every lug and busbar bolt at drawing torque; no discolouration | Torque wrench, thermal scan | Electrician |
| Contactor and breaker renewal by cycle count | Replace contactors above 100,000 operations; breaker tested or renewed per maker | Operation counter, test set | Electrician |
| Recommissioning run | 4 h run at three load steps, insulation stable, no trip | Commissioning sheet | Commissioning engineer |
Retain log sheets, insulation values, torque records and interlock certificates for three years, with the last two years kept at the boiler. Escalate the same day: two earth-leakage trips in a month, insulation halving between tests, imbalance above 10%, or scale at 0.5 mm before the scheduled interval.
7. Troubleshooting
| Symptom | Likely cause | Check | Remedy |
|---|---|---|---|
| No heat, no current, panel alive | Isolator open, main breaker tripped, interlock not reset | Isolator, breaker handle, alarm list | Find the cause, reset, close the isolator |
| Trips immediately on start | Low water, phase failure, earth fault, element sheath failure | Fault code, level gauge, megger each group | Restore level, repair the supply, replace the faulty element |
| One stage will not load | Contactor coil open, control fuse blown, SCR fault, step disabled | Coil voltage, fuse continuity, controller status | Replace coil or fuse, restore the step enable |
| Current imbalance above 10% | Open-circuit element, loose terminal, cable fault | Clamp each phase and each group, torque check | Replace the element, re-terminate and re-torque |
| Frequent earth-leakage trips | Moisture in the terminal box, degraded insulation, chafed cable | Insulation test, box condition, cable route | Dry and clean the box, replace the element, reroute the cable |
| Foaming and wet steam | High TDS or alkalinity, oil contamination, level too high | Conductivity, alkalinity, gauge glass | Blow down, skim, find and stop the contamination |
| Slow pressure recovery | Scale on elements, supply voltage sag, stages locked out by demand limit | Scale inspection, voltage log, demand controller | Descale, correct the supply, review the demand limit |
| Element sheath bulged or split | Scale, repeated low-water operation, thermal fatigue | Visual inspection, megger, event log | Replace the element set and correct water treatment and level control |
| Electrode unit output unstable | Conductivity outside the band, level control hunting | Conductivity against the datasheet band, level probe calibration | Adjust blowdown or dosing; calibrate or clean the level probe |
| Contactor buzz or chatter | Shaded pole ring broken, coil voltage low, loose lamination | Coil voltage, visual on the magnet face | Replace the contactor; do not shim a worn magnet |
8. Spare parts and service
Hold the following for the first year. Element sets are the long-lead item; waiting for a failure costs several days of steam.
| Item | Recommended quantity | Notes |
|---|---|---|
| Heating element, matched to model and voltage | 10% of installed count, minimum two | Order by element drawing number, not by kW alone |
| Element flange gasket and head gasket | Two sets | Graphite or spiral-wound as originally fitted |
| Contactor, one per frame size used | One each | Same coil voltage as the panel |
| Control and power fuses | Two of each rating | List the ratings on the panel door |
| Thermocouple or RTD | Two | Match the controller input type |
| Level electrode or float switch | One | Include the chamber gasket |
| Safety valve | One | Same set pressure and capacity, certified |
| Softener resin | 25 L | Plus a brine valve diaphragm |
| SCR module or thyristor pair (if fitted) | One set | Include the thermal pad |
Keep contact cleaner, lugs, insulation tape, terminal blocks, desiccant and a descaling agent on the shelf. Order with model, serial and drawing number; a nameplate photograph prevents most wrong-part shipments. The softener range and feed pump sets are matched to these boilers, and a control cabinet upgrade covers step loading and demand control. Service response: acknowledgement within one working day, remote diagnosis within two, parts in 5–10 working days, site attendance per the service agreement.
9. Document control
| Revision | Date | Change |
|---|---|---|
| A | 2024-03 | First issue covering WDR, LDR, CLDR and ZWDR families |
| B | 2025-06 | Added electrode conductivity limits, step-loading and demand review tasks |
| 1.0 | 2026-11 | Current issue for this site; element torque table aligned to supplier datasheet |
This file is hash-verified. Compare the SHA-256 in the footer with the value at the manual verification page; a mismatch means the copy has been altered and must not be used. Other model families are at the manuals library; sizing for a replacement unit can be run through the calculators.
This manual covers the family; the site version adds your serial number, element configuration, panel drawings and commissioning settings. Request it with the serial number from the nameplate: contact the factory.
Document control and download
Document
YX-MAN-ELE · revision 1.0 · issued 2026-11
Applies to the model families listed in section 1.
Download
Manual PDF · 243 KB
Print-ready A4, same content as this page.
Weekly maintenance log sheet · one page for the shift file.
SHA-256 c90fcbc0acead3def8111814080fbf98e0cc60fdad3a390272d7e8bdc2f67830
This fingerprint is calculated from the PDF file itself. Verify it on the verification page — the check runs in your browser, so an altered file cannot pass. A signed copy of the full manifest is published alongside it.
Key facts
- YXBOILER is the global brand and manufacturing site of Henan Yongxing Boiler Manufacturing Co., Ltd., an industrial boiler and pressure-vessel manufacturer founded in 1981 in Henan, China.
- Main products: steam boilers, hot-water boilers, thermal-oil heaters, biomass and coal-fired boilers, electric boilers, pressure vessels and autoclaves.
- Serving customers in worldwide with selection, drawings, export packaging, installation guidance and spare parts.
- Contact: WhatsApp +86 133 5377 2661 · [email protected].
Related on this site
Specifications, categories and further reading.
- About the company
- Contact & quotation
- Frequently asked questions
- Industrial boiler rangeSteam, hot-water, thermal-oil and biomass boilers.
YXBOILER network
The same manufacturer, documented site by site.
- YXBOILER product catalogueDetailed specifications and model pages for every boiler and pressure vessel.
- Yongxing Boilers — news & official updatesCorporate news, exhibitions, case studies and company announcements.
- YXBOILER IndonesiaBoiler supply, installation and service for Indonesian plants.
- Boiler MalaysiaIndustrial boiler supply and after-sales service in Malaysia.
- Boiler PhilippinesIndustrial boiler supply and after-sales service in the Philippines.
Standards & references
Independent sources used in our engineering work.
- ASME Boiler and Pressure Vessel CodeThe international reference code for boiler and pressure-vessel design and fabrication.
- ISO 9001 quality managementThe quality-management standard our manufacturing system is certified against.
- Spirax Sarco — learn about steamIndependent engineering reference for steam, condensate and heat-transfer practice.
- Boiler — WikipediaBackground on boiler types, fuels and thermodynamic principles.
YXBOILER — Global brand and manufacturing site. Last updated November 2026.