This manual covers the SZS series D-type double-drum water-tube boilers, fired on natural gas, LPG, light oil or heavy oil, in saturated steam ratings of 10 to 40 t/h at 1.6 and 2.5 MPa and in hot-water ratings of 7, 14 and 29 MW. It is written for the plant engineer, shift operator and maintenance technician who install, commission, run and inspect the unit. Every maintenance task carries a measurable acceptance limit, and values fixed by the ordered burner or water-treatment plant are flagged for confirmation against the site-specific manual.
1. Scope and model coverage
The SZS is a shop-assembled D-type boiler. Membrane water walls enclose the furnace on three sides; the fourth side is the convection bank between the drums, and gas leaves through the rear flue past the economiser and air preheater. The burner mounts on the front wall and fires horizontally along the furnace. A superheater can be fitted in the rear pass; this manual covers the saturated and hot-water variants, and superheated units follow the supplementary data sheet.
| Model | Capacity | Design pressure and temperature | Fuel | Typical duty |
|---|---|---|---|---|
| SZS10-1.6 | 10 t/h | 1.6 MPa, 204 °C saturated | Gas, LPG, light oil | Two-shift process steam |
| SZS15-1.6 | 15 t/h | 1.6 MPa, 204 °C saturated | Gas, light or heavy oil | Continuous process steam |
| SZS20-2.5 | 20 t/h | 2.5 MPa, 226 °C saturated | Gas, light oil | Process steam, small turbine supply |
| SZS25-2.5 | 25 t/h | 2.5 MPa, 226 °C saturated | Gas, light or heavy oil | Base-load industrial steam |
| SZS30-2.5 | 30 t/h | 2.5 MPa, 226 °C saturated | Gas, light oil | District heat and process steam |
| SZS40-2.5 | 40 t/h | 2.5 MPa, 226 °C saturated | Gas, light oil | Large plant base load |
| SZS7-1.0/95/70 | 7 MW | 1.0 MPa, 95/70 °C | Gas, light oil | Low-temperature district heating |
| SZS14-1.6/130/70, SZS29-1.6/130/70 | 14 and 29 MW | 1.6 MPa, 130/70 °C | Gas, light or heavy oil | Pressurised hot-water networks |
Capacity follows the saturated-steam equivalence of about 0.7 MW per t/h: 10 t/h is about 7 MW and 40 t/h about 28 MW. Steam models are described on the SZS oil and gas steam boiler page, hot-water models on the hot-water boiler page. Excluded: civil works, chimney steelwork beyond the outlet flange, fuel storage, the water-treatment plant unless ordered with the boiler, and electrical work upstream of the panel terminals. Burner gas-train settings follow the burner manual.
2. Site and utility requirements before delivery
Confirm every item below before dispatch. A shortfall found after delivery moves cost and delay to the site, and rear clearance cannot be corrected once the house is built. Record the values on the readiness sheet and return a signed copy. If demand is not yet fixed, size against the load profile using the load-duration method on the capacity selection pages.
| Item | Requirement | Tolerance and notes |
|---|---|---|
| Foundation and plinth | Reinforced concrete to the general arrangement, bolts cast in | Level ±3 mm, bolt centres ±2 mm, 25 mm grout |
| Burner front clearance | Space to swing the burner open and remove the nozzle | At least 1.5 m or burner length plus 0.5 m |
| Rear clearance | Access for economiser and preheater withdrawal | 2.0 m behind the flue, 0.8 m at drum ends |
| Headroom | Above drum, safety valve discharge and lifting beam | 1.0 m above the highest valve |
| Ventilation | Combustion and cooling air through two louvres | Free area ≥ 1.2 × burner air demand; room ≤ 45 °C |
| Feed water | Hardness ≤ 0.03 mmol/L, oxygen ≤ 0.05 mg/L, pH 8.8–9.3, iron ≤ 0.1 mg/L | Deaerator above 6 t/h; softener sized for make-up plus blowdown |
| Boiler water | pH 10–12, conductivity per drum pressure | ≤ 4000 µS/cm at 1.6 MPa, ≤ 3000 µS/cm at 2.5 MPa |
| Fuel gas | 20–35 kPa at the train inlet | +15% / −10%; calorific value within the burner data |
| Light oil | 0.6–1.0 MPa at the burner, viscosity ≤ 5 mm²/s | Ring main with return; heavy oil heated to 90–110 °C |
| Flue and chimney | Balanced draft, furnace −20 to −50 Pa at full load | Stack sized by dispersion calculation |
| Electrical supply | 380 V, three-phase, 50 Hz, neutral earthed | Voltage ±5%, earth resistance ≤ 4 Ω |
| Drainage and blowdown | Vented pit of at least 2 m³ with a cooling path | Discharge below 60 °C; blowdown line DN50 minimum |
3. Installation sequence
The sequence assumes a cured plinth and a weather-tight house. Do not start piping until the boiler is grouted and the expansion indicators are set, ; later jacking destroys the zero reference.
- Survey the plinth and mark the centre lines and bolt positions. Acceptance: level ±3 mm, diagonals equal within 5 mm.
- Unload with a crane rated for the shipping weight, lifting only from the marked lugs. Acceptance: no casing or tube distortion.
- Set the boiler on packers and align the drum axis. Acceptance: centre line ±2 mm in both directions.
- Grout the base frame with non-shrink grout and cure before filling. Acceptance: no voids at the corners.
- Fit the expansion indicators and set zero at 20 °C. Acceptance: pointer on zero, scale readable from the operating floor.
- Assemble the rear flue, economiser and air preheater with new gaskets. Acceptance: 5 kPa air test with soap solution shows no bubbles.
- Erect duct and chimney, then measure draft with the induced-draft fan running. Acceptance: −20 to −50 Pa at the furnace outlet.
- Install the burner and check nozzle protrusion and throat clearance. Acceptance: protrusion ±2 mm, door swings 90° clear of the casing.
- Pipe the feed line from deaerator through pump and economiser to the drum, with a non-return valve. Acceptance: no load on the drum nozzles.
- Install the steam or hot-water header on spring hangers with a 1:100 fall. Acceptance: hangers carry the pipe weight, no cold pull at the flange.
- Mount safety valves, pressure gauges with syphons, thermowells and level transmitters. Acceptance: gauge range 1.5–2 times design pressure.
- Complete the electrical work to the panel terminals and earth the frame. Acceptance: insulation ≥ 1 MΩ at 500 V, earth ≤ 4 Ω.
- Fill with treated water at 20–50 °C, vent the drum, raise to working pressure. Acceptance: no weeping at manholes or expanded joints.
- Hydrostatic test at 1.5 times design, hold 30 minutes, drain and flush. Acceptance: no pressure drop and no permanent deformation.
4. Commissioning and handover
Commissioning starts after the hydrostatic test and internal inspection. Fill with treated water at 20–50 °C, vent every high point, and confirm that the gauge glass and transmitter agree within 5 mm before lighting.
The hydrostatic test pressure is 1.5 times design: 2.4 MPa for the 1.6 MPa units and 3.75 MPa for the 2.5 MPa units. Hold for 30 minutes at a water temperature of 20–50 °C with a calibrated gauge on the drum and the safety valves gagged. Acceptance is no pressure drop, no weeping at any joint and no visible deformation, following the practice of GB/T 16508 and TSG G0001.
Set the burner at low fire, then high fire, on the fuel named in the order. For natural gas, target 3.0–3.5% oxygen at low fire and 3.0% at high fire, about 15–20% excess air and 9.5–10.5% carbon dioxide; carbon monoxide must stay below 50 ppm. Bring stack temperature within 20 °C of design at rated load and record every damper position on the commissioning curve; later maintenance is judged against it. The matched burner package manual governs gas-train pressures and scanner settings.
| Interlock | Simulated condition | Expected result |
|---|---|---|
| Extra-low water level | Drain the float chamber until the LL electrode is dry | Burner trips within 3 s, alarm sounds, reset blocked until level returns |
| High water level | Raise level above the HH electrode | Feed pump stops, alarm sounds, burner stays on |
| Flame failure | Close the manual gas cock at low fire | Main valve closes within 3 s, post-purge runs, lockout without auto-restart |
| Low gas pressure | Drop train pressure below 50% of set point | Burner trips, alarm latched, purge before restart |
| High gas pressure | Raise pressure above 110% of set point | Burner trips, alarm latched, relief not lifted |
| High steam pressure | Lower the pressure switch set point below working pressure | Trip at set pressure plus 0.05 MPa; safety valve must not lift |
| Combustion air failure | Stop the forced-draft fan at low fire | Trip within 2 s, damper closes, alarm sounds |
| Low feed-water pressure | Throttle the feed valve below 80% of set point | Burner trips, standby pump starts where fitted |
Run 4 hours at 50–75% load, then 24 hours at normal plant load, logging level, steam pressure and temperature, feed-water and stack temperature, oxygen, carbon monoxide and draft hourly. Acceptance: no unexplained trip, stack temperature stable within 10 °C, level held within ±10 mm on automatic control, no leaks. Handover documents are the as-built arrangement, pressure-part material certificates, hydrostatic record, safety valve setting record, interlock test sheet, burner commissioning curve, wiring diagram and this manual.
5. Normal operation
Start-up from cold. Confirm normal level, open vent and burner off. Purge for 5 minutes at 25% air flow, five volume changes. Light at minimum fire, hold until 0.2 MPa, then close the vent. Raise pressure at no more than 0.03 MPa per minute and keep the drum top-to-bottom difference below 40 K; working pressure takes 2–3 hours. Load at no more than 10% of capacity per minute.
Start-up from hot standby. With the drum at 0.3–0.5 MPa and level at −50 mm, purge for 5 minutes, light and raise load at 10% per minute, keeping drum metal rise below 1.0 °C per minute. After 8 hours on standby, check the gauge glass before purging; a leaking non-return valve can fill the drum.
| Parameter | Normal band | Action if outside |
|---|---|---|
| Drum water level | ±10 mm of the normal line | Compare with gauge glass, blow down, check transmitter |
| Steam pressure | 1.6 ± 0.05 MPa or 2.5 ± 0.08 MPa | Check modulation and pressure transmitter |
| Steam temperature | Saturation ±5 °C (204 or 226 °C) | Check for carryover |
| Feed water after economiser | At least 40 K below saturation | Check economiser fouling and deaerator |
| Stack temperature | Within 20 °C of the clean baseline | Blow soot, check for scale |
| Oxygen at outlet | 3.0–3.5% | Trim air damper, check analyser |
| Carbon monoxide | ≤ 50 ppm | Check nozzle, flame shape and excess air |
| Furnace draft | −20 to −50 Pa | Check ID fan, damper and flue blockage |
| Drum metal difference | ≤ 40 K top to bottom | Reduce firing rate, extend warm-up |
Normal shutdown. Reduce to 20% load at 10% per minute, purge 5 minutes, close the main valve and stop the burner. Run the fan 10 minutes to clear the furnace and flue, then close the air damper. Top up to normal level because the water shrinks as it cools, and blow down only below 0.2 MPa.
Emergency shutdown. Press the emergency stop, which closes the main fuel valve and trips the burner. Keep the fan running if unburnt fuel is suspected, and do not open the furnace until a 5-minute purge is complete. Never dump water from a hot boiler or lift a safety valve by hand to speed up pressure reduction. Record the cause, pressure and level.
Lay-up over 30 days. Wet lay-up: fill completely with condensate or demineralised water dosed to pH 10.5–11.5 with 200 mg/L oxygen scavenger, blanket with nitrogen at 0.05–0.1 MPa, and check chemistry weekly. Dry lay-up: drain and dry, place 1.0 kg of desiccant per cubic metre of water volume in trays on the drum, seal the manholes and keep relative humidity below 40%, renewing the desiccant monthly.
6. Maintenance schedule
Intervals assume gas or light oil, treated water and 6,000 base-load hours a year; halve them for heavy oil or more than two starts a day. The energy consumption pages give the baseline stack temperature and efficiency; the US Department of Energy steam resources give a wider audit benchmark.
6.1 Daily (each shift)
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Drum level | Gauge glass within ±10 mm of the transmitter; blow the glass until clear | Gauge glass, trend | Operator |
| Pressure and temperature | Within the section 5 band; within 5 °C of saturation | Panel, calibrated gauge | Operator |
| Burner and gas train | Flame stable; scanner signal ≥ 60% of commissioning value; gas 20–35 kPa | Scanner display, gauge | Operator |
| Oxygen and stack temperature | O2 3.0–3.5%; stack within 20 °C of baseline | Analyser, thermocouple | Operator |
| Soot blowers | Rear bank and economiser blowers once per shift on oil, once per 8 h on gas above 80% load; steam 0.8–1.0 MPa | Blower control | Operator |
| Bottom blowdown | 10–15 s; conductivity ≤ 4000 µS/cm (1.6 MPa) or 3000 µS/cm (2.5 MPa) | Valve, conductivity meter | Operator |
| Feed pump and deaerator | Current within 10% of commissioning; deaerator 104 ± 2 °C; oxygen ≤ 0.05 mg/L | Ammeter, DO meter | Operator |
| Expansion indicators | Reading within ±2 mm of the chart value for the drum temperature | Indicator, chart | Operator |
| Leaks and casing | No steam, water or gas leak; casing ≤ ambient plus 25 K | Visual, IR thermometer | Operator |
6.2 Monthly
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Level transmitter calibration | Five points at 0/25/50/75/100%; error ≤ ±5 mm; contacts at ±50 and ±75 mm | Calibrator, sight glass | Instrument technician |
| Safety valve manual lift | Lift at 75% of set pressure or above; reseats without wire drawing | Lever, pressure gauge | Shift engineer |
| Flame scanner and igniter | Lens clean, signal ≥ 60%, spark gap 2.5 ± 0.2 mm | Scanner test, feeler gauge | Technician |
| Air preheater cold end | Metal ≥ 130 °C on oil and ≥ 90 °C on gas; drain flowing; no acid smear | Thermocouple, sight glass | Technician |
| Feed-water analysis | Hardness ≤ 0.03 mmol/L, iron ≤ 0.1 mg/L, pH 8.8–9.3; softener cycle verified | Lab kit, softener log | Chemist |
| Burner linkage | Damper positions match the curve at low, mid and high fire; backlash ≤ 2° | Curve sheet, protractor | Technician |
| Alarm annunciation | Every alarm tested; horn and beacon operate | Test list | Instrument technician |
| Soot blower travel | Full stroke without sticking; nozzles aligned within ±3 mm | Manual stroke, drawing | Fitter |
6.3 Quarterly and semi-annual
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Water-side inspection (semi-annual) | Open handholes; scale ≤ 0.5 mm, no sludge blanket in the lower drum | Boroscope, scraper | Boiler engineer |
| Steam purity | Steam conductivity ≤ 1 µS/cm above feed water | Sample cooler, meter | Chemist |
| Flue-gas analysis | CO ≤ 50 ppm, excess air 15–20%, NOx within permit | Flue analyser | Technician |
| Casing and refractory survey | No hot spot above ambient plus 25 K; front-wall cracks ≤ 3 mm | IR camera, crack gauge | Boiler engineer |
| Electrical inspection | Insulation ≥ 1 MΩ at 500 V, earth ≤ 4 Ω, currents balanced within 5% | Insulation and earth testers | Electrician |
| Drum supports (semi-annual) | Sliding pads free, anchor nuts tight, 3 mm clearance at guides | Torque wrench, feeler | Fitter |
| Air preheater tightness | Gas-to-air leakage ≤ 5% by oxygen rise across the unit | O2 readings | Technician |
6.4 Annual shutdown inspection
| Task | What to check / acceptance | Tool or reference | Who |
|---|---|---|---|
| Drum internals and steam-water separator | Open both manholes, clean internals, inspect separator vanes, baffles, feed pipe and blowdown pipe for cracks or distortion; gaps ±1 mm of drawing; renew manhole gaskets | Boroscope, drawing, gaskets | Service engineer |
| Tube wall thickness survey | Ultrasonic survey of water walls, convection bank and economiser; full survey every 3 years, 10% spot check between, concentrated on the burner zone; alarm at 90% of nominal (4.5 mm), replace below 80% (4.0 mm) | UT gauge, tube chart | NDT inspector |
| Hydrostatic test where due | 1.5 × design (2.4 or 3.75 MPa) for 30 minutes; no drop, no weeping | Test pump, master gauge | Engineer and inspector |
| Safety valve overhaul | Strip and lap seats, bench-set to ≤ design pressure on a certified gauge, accumulation ≤ 10%, re-seal and record | Bench rig, master gauge | Service engineer |
| Soot blower overhaul | Lance straight within 2 mm, nozzles clear, chain tension correct, limit switches working | Straight edge, chain gauge | Fitter |
| Air preheater cold end | Clean elements; wall loss ≤ 30%, replace beyond; check expansion plates | Thickness gauge | Fitter |
| Refractory and front wall | Cracks ≤ 3 mm, no spalling at the throat; patch with matching castable | Hammer test, castable | Refractory mason |
| Expansion indicators and drum supports | Record cold reading, compare with the last hot reading, reset zero if within ±1 mm of chart; rollers free | Indicator, chart | Boiler engineer |
| Deaerator and feed system | Internals clean, nozzles clear, oxygen ≤ 0.05 mg/L after restart, safety valve free | Inspection cover, DO meter | Boiler engineer |
7. Troubleshooting
| Symptom | Likely cause | Check | Remedy |
|---|---|---|---|
| Pressure falls at constant load | Fouled tubes, wrong air/fuel ratio | Stack temperature, O2, burner position | Blow soot, trim ratio, check modulation signal |
| Stack temperature 30 °C above baseline | Soot on the bank, water-side scale | O2 before and after the bank, water side | Operate blowers, descale, reseat baffles |
| Wet steam or carryover | High solids, damaged separator, high level | Steam conductivity, internals, level trend | More blowdown, repair separator, lower level |
| Low-water trip on start-up | Transmitter drift, closed feed valve, air lock | Glass against transmitter, pump pressure | Recalibrate, open valve, vent feed line |
| Burner lockout during a run | Dirty scanner, gas pressure excursion | Scanner signal, train pressure, flame shape | Clean scanner, reset after full purge |
| Make-up rises and pressure drops | Tube or expanded-joint leak | Water balance, hydro test, UT survey | Isolate, locate by section, replace or re-expand |
| Acid smell at the preheater | Cold end below dew point at low load | Cold-end temperature, drain flow | Raise inlet air temperature, keep load above 30% |
| High carbon monoxide | Lean flame, dirty nozzle, closed secondary air | O2 and CO together, nozzle condition | Clean nozzle, open secondary air, re-trim |
| Safety valve weeps | Seat damage, debris, set pressure low | Setting record, seat condition | Lap or replace seat, bench-set and re-seal |
8. Spare parts and service
Hold the following for the first year; add a second set if there is no standby unit.
| Item | Quantity | Notes |
|---|---|---|
| Manhole and handhole gaskets | Two full sets | Graphite or spiral-wound; never reuse a compressed gasket |
| Gauge glass and packing | Two sets | Match glass length to the fitting |
| Level electrodes | One set | Same model, calibration sheet kept |
| Burner nozzle and electrodes | One set | Size per burner data sheet |
| Flame scanner | One | Interchangeable with the fitted unit |
| Gas train filter element | Two | Renew at each annual shutdown |
| Soot blower nozzles | Four | Match the lance thread |
| Refractory castable | 50 kg | Same grade as the front wall, stored dry |
Stock descaler, oxygen scavenger, softener salt and anti-seize compound. Order by model, serial number, drawing number and position number; a nameplate photograph shortens the check. The feed-water pump and control cabinet are listed separately when supplied as part of the package. Henan Yongxing Special Equipment Co., Ltd. acknowledges parts enquiries within one working day, dispatches stock items within two, and puts an engineer on site within five working days for a pressure-part or control fault; emergency cover is on the number in the order confirmation.
9. Document control
| Revision | Date | Change |
|---|---|---|
| A | 2019-06 | First issue, SZS10 to SZS40 |
| B | 2022-03 | Added hot-water models, O2 trim and the 3-year ultrasonic survey |
| C | 2025-11 | Revised maintenance tables, valve re-sealing and lay-up limits |
This file is hash-verified. The SHA-256 digest of the published document is shown on the verification page; a copy whose digest does not match is uncontrolled. Check the digest at the manual verification page before relying on a printed copy, and compare the revision letter with the table above; earlier revisions remain in the manual library. The boiler is designed and built to GB/T 16508 and TSG G0001, with third-party inspection available on request; no other certification is implied.
Burner settings, water limits and chimney draught are fixed per order, so ask for the site-specific manual with your serial number before the first annual inspection. Send the serial number, model and a nameplate photograph through the contact page for the matching document and current spare-parts list.
Document control and download
Document
YX-MAN-SZS · revision 1.0 · issued 2026-11
Applies to the model families listed in section 1.
Download
Manual PDF · 253 KB
Print-ready A4, same content as this page.
Weekly maintenance log sheet · one page for the shift file.
SHA-256 940f007ea722c9c6698924cd3e16b06ac6f978f3ced3a2097ce71c71d0bbdc96
This fingerprint is calculated from the PDF file itself. Verify it on the verification page — the check runs in your browser, so an altered file cannot pass. A signed copy of the full manifest is published alongside it.
Key facts
- YXBOILER is the global brand and manufacturing site of Henan Yongxing Boiler Manufacturing Co., Ltd., an industrial boiler and pressure-vessel manufacturer founded in 1981 in Henan, China.
- Main products: steam boilers, hot-water boilers, thermal-oil heaters, biomass and coal-fired boilers, electric boilers, pressure vessels and autoclaves.
- Serving customers in worldwide with selection, drawings, export packaging, installation guidance and spare parts.
- Contact: WhatsApp +86 133 5377 2661 · [email protected].
Related on this site
Specifications, categories and further reading.
- About the company
- Contact & quotation
- Frequently asked questions
- Industrial boiler rangeSteam, hot-water, thermal-oil and biomass boilers.
YXBOILER network
The same manufacturer, documented site by site.
- YXBOILER product catalogueDetailed specifications and model pages for every boiler and pressure vessel.
- Yongxing Boilers — news & official updatesCorporate news, exhibitions, case studies and company announcements.
- YXBOILER IndonesiaBoiler supply, installation and service for Indonesian plants.
- Boiler MalaysiaIndustrial boiler supply and after-sales service in Malaysia.
- Boiler PhilippinesIndustrial boiler supply and after-sales service in the Philippines.
Standards & references
Independent sources used in our engineering work.
- ASME Boiler and Pressure Vessel CodeThe international reference code for boiler and pressure-vessel design and fabrication.
- ISO 9001 quality managementThe quality-management standard our manufacturing system is certified against.
- Spirax Sarco — learn about steamIndependent engineering reference for steam, condensate and heat-transfer practice.